Champion Iron Overcomes Shipment Hurdles While Advancing Green Steel Projects

7:03pm on Monday 2nd of June, 2025 AEST Mining
Read Story

Champion Iron Overcomes Shipment Hurdles While Advancing Green Steel Projects

7:03pm on Monday 2nd of June, 2025 AEST
Key Points
  • Q3 FY2025 revenues of $363.2 million and EBITDA of $88.2 million
  • 14-day shipment disruption at Bloom Lake load-out facility caused stockpile buildup
  • DRPF project on schedule with commissioning expected December 2025
  • Binding partnership agreement signed with Nippon Steel and Sojitz for Kami Project development