middle.news
Tlou Energy Nears Power Generation Milestone at Lesedi Project in 2025
12:39pm on Thursday 30th of January, 2025 AEDT
•
Energy
Read Story
Tlou Energy Nears Power Generation Milestone at Lesedi Project in 2025
12:39pm on Thursday 30th of January, 2025 AEDT
Key Points
Lesedi substation over 90% complete, commissioning expected Q1 2025
100km transmission line construction finished, connecting to Botswana grid
Gas production optimization underway to ensure stable power generation
Power generation equipment discussions ongoing for phased installation
Read Story
middle.
Tap to Read
Tap the card to read the full analysis
about
Tlou Energy (ASX:TOU)
OPEN ARTICLE