Tlou Energy Nears Power Generation Milestone at Lesedi Project in 2025
7:03pm on Monday 2nd of June, 2025 AEST
•
Energy
Read Story
Tlou Energy Nears Power Generation Milestone at Lesedi Project in 2025
7:03pm on Monday 2nd of June, 2025 AEST
Key Points
Lesedi substation over 90% complete, commissioning expected Q1 2025
100km transmission line construction finished, connecting to Botswana grid
Gas production optimization underway to ensure stable power generation
Power generation equipment discussions ongoing for phased installation