Philsaga Mining Delays Tigerway Decline Completion to December 2025 Amid Operational Challenges
11:54am on Monday 3rd of February, 2025 AEDT
•
Mining
Read Story
Philsaga Mining Delays Tigerway Decline Completion to December 2025 Amid Operational Challenges
11:54am on Monday 3rd of February, 2025 AEDT
Key Points
Tigerway decline development temporarily halted at 620 meters depth
4,217 meters of main decline and 1,338 meters of accessory drives completed by December 2024
Expenditure of US$43.4 million on main decline, within original US$54 million budget
Operational challenges include COVID-19 delays, 7.2 magnitude earthquake, and ventilation issues