middle.news

Philsaga Mining Delays Tigerway Decline Completion to December 2025 Amid Operational Challenges

11:54am on Monday 3rd of February, 2025 AEDT Mining
Read Story

Philsaga Mining Delays Tigerway Decline Completion to December 2025 Amid Operational Challenges

11:54am on Monday 3rd of February, 2025 AEDT
Key Points
  • Tigerway decline development temporarily halted at 620 meters depth
  • 4,217 meters of main decline and 1,338 meters of accessory drives completed by December 2024
  • Expenditure of US$43.4 million on main decline, within original US$54 million budget
  • Operational challenges include COVID-19 delays, 7.2 magnitude earthquake, and ventilation issues
Read Story
middle.

Tap to Read

Tap the card to read the full analysis
about X64
OPEN ARTICLE