middle.news
Philsaga Mining Delays Tigerway Decline Completion to December 2025 Amid Operational Challenges
5:44pm on Sunday 1st of June, 2025 AEST
•
Mining
Read Story
Philsaga Mining Delays Tigerway Decline Completion to December 2025 Amid Operational Challenges
5:44pm on Sunday 1st of June, 2025 AEST
Key Points
Tigerway decline development temporarily halted at 620 meters depth
4,217 meters of main decline and 1,338 meters of accessory drives completed by December 2024
Expenditure of US$43.4 million on main decline, within original US$54 million budget
Operational challenges include COVID-19 delays, 7.2 magnitude earthquake, and ventilation issues
Read Story
middle.
Tap to Read
Tap the card to read the full analysis
about
X64
OPEN ARTICLE