Philsaga Mining Delays Tigerway Decline Completion to December 2025 Amid Operational Challenges

5:44pm on Sunday 1st of June, 2025 AEST Mining
Read Story

Philsaga Mining Delays Tigerway Decline Completion to December 2025 Amid Operational Challenges

5:44pm on Sunday 1st of June, 2025 AEST
Key Points
  • Tigerway decline development temporarily halted at 620 meters depth
  • 4,217 meters of main decline and 1,338 meters of accessory drives completed by December 2024
  • Expenditure of US$43.4 million on main decline, within original US$54 million budget
  • Operational challenges include COVID-19 delays, 7.2 magnitude earthquake, and ventilation issues