Processing Breakthrough Cuts Costs 93.5% as ARR Advances Billion-Dollar Rare Earth Project
American Rare Earths has expanded its Halleck Creek rare earth resource by 12.2% and achieved a metallurgical breakthrough that slashes processing volumes by over 90%, underpinning a robust updated scoping study with strong financial metrics.
- JORC resource increased to 2.63 billion tonnes at 3,292 ppm TREO
- 10x rare earth upgrade achieved via low-cost beneficiation, reducing processing volumes by 93.5%
- Updated scoping study shows NPV10% of US$558M (3 Mtpa) and US$1.17B (6 Mtpa) with IRRs above 24%
- License granted for test mining and bulk sampling at Cowboy State Mine
- Strong financial position with $12 million cash and strategic funding interest from U.S. Export-Import Bank
Resource Expansion and Grade Improvement
American Rare Earths (ASX: ARR) has reported a significant 12.2% increase in its Halleck Creek Mineral Resource, now estimated at 2.63 billion tonnes with an average grade of 3,292 ppm total rare earth oxides (TREO). This upgrade, announced in early February 2025, notably includes a 29.7% growth in the Red Mountain area and a 29.4% expansion at the Cowboy State Mine, the project's initial development phase. These results reinforce Halleck Creek’s status as one of North America’s largest rare earth deposits, with the resource remaining open for further expansion both at depth and along strike.
Metallurgical Breakthrough Enhances Project Viability
In a breakthrough metallurgical development, ARR achieved a 10-fold upgrade in rare earth concentration at scale using conventional, low-cost beneficiation techniques such as gravity spirals and induced roll magnetic separation. This process elevates the grade from 3,438 ppm to an impressive 37,200 ppm TREO, while removing 93.5% of non-rare earth material early in processing. The result is a dramatic reduction in processing volumes by over 90%, which is expected to lower operating costs and validate key assumptions in the company’s scoping study. Ongoing optimisation efforts aim to further improve recoveries and impurity removal.
Updated Scoping Study Confirms Robust Economics
The updated scoping study, released in March 2025, integrates the expanded resource and metallurgical advances, presenting a compelling economic case for Halleck Creek. The base case scenario, targeting 3 million tonnes per annum (Mtpa) production, delivers a net present value (NPV10%) of US$558 million and an internal rate of return (IRR) of 24%, with a modest capital expenditure (CAPEX) of US$456 million and a payback period of 2.7 years. A more ambitious 6 Mtpa production case nearly doubles the NPV to US$1.17 billion, with an IRR of 28.4% and CAPEX of US$737 million, shortening the payback to 1.8 years. Notably, only about 2.4% of the total resource is planned to be mined in the first 20 years, indicating substantial long-term growth potential.
Advancing Project Development and Permitting
ARR secured a crucial license enabling test mining, trenching, and bulk sampling at the Cowboy State Mine. This milestone allows the company to collect bulk material samples essential for pilot plant testing and refining processing techniques at its Wyoming facility. The streamlined permitting environment in Wyoming, combined with the project's location on state land, positions Halleck Creek for efficient development and supports ARR’s strategy to establish a domestic rare earth supply chain aligned with U.S. critical mineral priorities.
Corporate and Financial Strength
On the corporate front, ARR repaid $2 million plus interest on a $3 million promissory note from Cobalt Blue Holdings, receiving shares as part of amended loan terms. The company maintains a strong cash position of $12 million as of March 31, 2025, supplemented by strategic funding interest including a letter of interest from the U.S. Export-Import Bank for up to US$456 million in project finance, grant funding from the State of Wyoming, and ongoing engagement with BMO Capital Markets to secure joint ventures and offtake agreements. These financial foundations underpin ARR’s capacity to advance Halleck Creek through pre-feasibility and pilot plant stages.
Strategic Implications
Halleck Creek’s scale, grade, and processing advancements position American Rare Earths as a key player in reshaping the U.S. rare earths industry. The project’s potential to reduce reliance on imports, particularly from China, aligns with growing geopolitical and economic imperatives for critical mineral independence. As ARR progresses towards pilot plant operations and final investment decisions, the market will be watching closely for further validation of project economics and successful financing arrangements.
Bottom Line?
With resource growth and processing breakthroughs in hand, American Rare Earths is poised to transform U.S. rare earth supply—next steps hinge on pilot plant success and financing.
Questions in the middle?
- How will pilot plant test results impact the final project flowsheet and economics?
- What are the timelines and terms for securing full project financing and offtake agreements?
- How might evolving rare earth market dynamics affect ARR’s development strategy and valuation?