Copper Offtake Talks and Gold Processing Delays: What Risks Lie Ahead for Horseshoe Metals?
Horseshoe Metals has extended the gold surface materials processing option at Horseshoe Lights to mid-2025, while advancing copper Direct Shipping Ore activities and negotiating key offtake deals.
- Gold processing option extended to 30 June 2025 for metallurgical test completion
- Composite samples confirm gold grades between 0.32 and 2.43 g/t
- Melody Gold plans to retreat up to 500,000 tonnes per annum of gold surface material
- Horseshoe retains full rights to copper and mixed copper/gold surface and subsurface materials
- Copper DSO workstreams progressing with offtake and funding negotiations underway
Gold Surface Materials Processing Extension
Horseshoe Metals Ltd (ASX: HOR) has announced an extension of the gold surface materials processing option at its Horseshoe Lights project to 30 June 2025. This extension allows Melody Gold Pty Ltd, the option holder, additional time to complete metallurgical test work on composite samples derived from historic gold leach vats and rehandle stockpiles. The samples, ranging from 0.32 to 2.43 grams per tonne (g/t) gold, have been assayed to confirm their grade, supporting Melody Gold’s plan to treat up to 500,000 tonnes per annum using gravity recovery methods to produce a gold-copper-silver concentrate.
Strategic Retention of Copper Rights
While Melody Gold focuses on the gold surface materials, Horseshoe Metals retains full rights to copper and mixed copper/gold surface materials, as well as all subsurface metals. This strategic retention underpins the company’s broader redevelopment ambitions at Horseshoe Lights, a historically significant copper-gold mine with substantial mineral resources. The company is actively advancing several workstreams related to Direct Shipping Ore (DSO) copper sales, aiming to generate early cash flow from existing high-grade copper stockpiles.
Advancing Copper DSO and Offtake Negotiations
Horseshoe Metals is progressing negotiations with multiple well-known commodity traders to secure copper offtake agreements and funding arrangements. These efforts are critical to fast-tracking the redevelopment of the copper-gold system at Horseshoe Lights. The company’s Non-Executive Director, Kate Stoney, highlighted the unique position Horseshoe holds as a junior miner with 100% ownership of a copper asset capable of delivering immediate cash flow, supported by multiple low-capital development options and significant exploration upside.
Project Background and Resource Overview
The Horseshoe Lights project encompasses a historic open pit and associated stockpiles, with a total mineral resource including measured, indicated, and inferred categories. The resource includes approximately 128,600 tonnes of copper and over 30,000 ounces of gold in the main deposit, alongside additional copper and silver in flotation tailings and stockpiles. The project’s geology is characteristic of a Volcanogenic Hosted Massive Sulphide (VMS) deposit, with a complex history of mining phases and metallurgical processing.
Looking Ahead
With the gold processing option extended and copper DSO activities gaining momentum, Horseshoe Metals is positioning itself to unlock significant value from the Horseshoe Lights project. The company’s multi-staged development approach aims to deliver material cash flow in the near term while exploring the considerable upside potential of its copper-gold assets.
Bottom Line?
Horseshoe Metals is set to unlock value through gold retreatment and copper DSO, with key test results and offtake deals on the horizon.
Questions in the middle?
- What will the final metallurgical test results reveal about the gold surface materials’ processing viability?
- How soon can Horseshoe Metals commence copper DSO shipments and generate meaningful cash flow?