Vault Minerals Unveils 33% KoTH Ore Reserve Boost and $92M Plant Upgrade

1:47am on Monday 2nd of June, 2025 AEST Mining
Read Story

Vault Minerals Unveils 33% KoTH Ore Reserve Boost and $92M Plant Upgrade

1:47am on Monday 2nd of June, 2025 AEST
Key Points
  • 33% increase in KoTH open pit Ore Reserve to 2.2 million ounces
  • Stage 2 plant upgrade to 7.5mtpa processing capacity by late Q2 FY27
  • Capital expenditure of $92 million for Stage 2, internally funded
  • Average gold production of 215,000 ounces annually over next five years