QPM Raises $10M at $0.031 Per Share to Fund 112MW Power Station

Energy By Maxwell Dee 3 min read

QPM Energy Limited has successfully raised $10 million through an oversubscribed placement and launched a $2 million Share Purchase Plan to fast-track the 112MW Isaac Power Station, the cornerstone of its Isaac Energy Hub.

  • Oversubscribed $10 million placement at $0.031 per share
  • Launch of $2 million Share Purchase Plan for eligible shareholders
  • Funds to procure critical long lead items including GE Vernova gas turbines
  • Development of 112MW Isaac Power Station as part of Isaac Energy Hub
  • Placement shares to rank equally with existing shares, settlement expected 2 July 2025
Image source middle. ©

Capital Raise to Propel Energy Ambitions

QPM Energy Limited (ASX, QPM) has announced a successful $10 million placement, priced at $0.031 per share, to institutional and sophisticated investors. The placement was oversubscribed, reflecting strong confidence from both existing and new investors in QPM’s vision for the Isaac Energy Hub. Complementing this, the company has launched a $2 million Share Purchase Plan (SPP) to enable retail shareholders to participate on the same terms, further broadening the base of support for its growth strategy.

Focus on the Isaac Power Station

The capital raised will be directed primarily towards accelerating the development of the 112MW Isaac Power Station (IPS), the first major asset within the Isaac Energy Hub. This project represents a significant step for QPM, aiming to establish a platform for expanding its electricity generation portfolio. The recent feasibility study results, released in June 2025, underscored the project’s potential to deliver robust earnings and shareholder value, underpinning investor enthusiasm.

Strategic Procurement and Project Advancement

Key to the accelerated timeline is the procurement of critical long lead items, notably two 55.8MW aeroderivative gas turbines supplied by GE Vernova. Securing these turbines early is expected to mitigate supply chain risks and expedite construction phases. The funds from the placement and SPP will also support ongoing development activities and project financing efforts, positioning QPM to move swiftly from planning to execution.

Investor Participation and Market Impact

The placement shares will be issued in a single tranche and rank equally with existing shares, with settlement anticipated on 2 July 2025. The SPP offers eligible shareholders the opportunity to invest up to $30,000 without brokerage or transaction fees, with the company retaining discretion to accept oversubscriptions or scale back applications. This inclusive approach aims to maintain strong retail investor engagement alongside institutional backing.

Looking Ahead

With the capital raise complete, QPM’s management is poised to advance the Isaac Power Station development aggressively. The project’s success will be critical in validating the broader Isaac Energy Hub concept and unlocking future growth avenues in electricity generation. Market watchers will be keen to monitor progress milestones and subsequent financial updates as QPM transitions from funding to operational phases.

Bottom Line?

QPM’s capital raise sets the stage for a pivotal phase in its energy ambitions, but execution risks and project timelines will be closely watched.

Questions in the middle?

  • How quickly can QPM secure project financing beyond the initial procurement phase?
  • What are the anticipated timelines for construction and commissioning of the Isaac Power Station?
  • How will the company balance institutional and retail investor interests through the SPP and future capital raises?