Robex Resources reports steady progress on its Kiniero Gold Project in Guinea, maintaining schedule and budget for first gold production in late 2025. Key construction milestones and drilling results underpin confidence in the project’s near-term potential.
- Kiniero Gold Project construction on schedule and within budget
- First gold production targeted for Q4 calendar year 2025
- Phase 1 grade control drilling at Mansounia completed with high-grade results
- Mill installation and process plant concrete works nearing completion
- Mining contracts signed and equipment mobilized, tailings facility liner installed
Steady Progress on Kiniero Gold Project
Robex Resources Inc. continues to advance its Kiniero Gold Project in Guinea with construction activities tracking well against planned timelines and budgets. The company remains on course to achieve its goal of first gold production in the fourth quarter of calendar year 2025, a milestone that would mark a significant step forward for this West African gold development.
Recent updates highlight that major concrete works for the process plant are approximately 97% complete, with the final pours recently finished. Mill installation is underway, including the alignment of baseplates and erection of the SAG mill shell, supported by the assembly of a 300-tonne crane for heavy lifts. Structural steel shipments have arrived on site, and mechanical, piping, and electrical teams are mobilizing to support the next phases of construction.
Drilling and Mining Preparations
On the exploration front, phase 1 grade control drilling at the Mansounia pit has been completed, returning high-grade gold results that reinforce the project's resource potential. Drilling at the Sabali pit is ongoing, with nearly 17,000 meters drilled and close to 85,000 samples collected, though assay results are still pending. These drilling programs are critical for defining ore zones ahead of mining operations.
Mining contracts have been signed, and equipment mobilization is underway, signaling readiness to commence extraction activities. Additionally, the tailings storage facility’s Phase 1A liner installation is complete, and embankment construction is progressing as weather permits. Infrastructure developments such as overland piping installation and geotechnical drilling for a solar farm are also advancing, underscoring the comprehensive nature of site preparation.
Safety and Operational Outlook
Robex proudly reports a strong safety record with no lost time injuries recorded over more than 3.6 million hours worked since January 2023. This safety performance reflects well on the company’s operational discipline and contractor management as the project scales up.
Looking ahead, Robex plans to complete all remaining concrete works, continue mill and steelwork erection, finalize drilling at Sabali, and award key contracts for ore haulage, laboratory services, and power station operations. Procurement of critical spares and reagents is also underway to support smooth commissioning and production ramp-up.
While the project remains on track, Robex’s forward-looking statements prudently acknowledge risks including geopolitical instability in West Africa, commodity price fluctuations, operational delays, and financing challenges. These factors will require ongoing management attention as Kiniero moves closer to production.
Bottom Line?
With construction milestones steadily achieved, Robex is poised to deliver first gold at Kiniero by late 2025, but geopolitical and operational risks remain watchpoints.
Questions in the middle?
- When will assay results from Sabali drilling be released, and how might they impact resource estimates?
- What are the specifics and terms of the newly signed mining and haulage contracts?
- How is Robex managing geopolitical and security risks in Guinea to safeguard project timelines?