How Lindian Resources Is Powering Up Kangankunde for 2026 Rare Earths Output

8:34am on Wednesday 8th of October, 2025 AEDT Mining
Read Story

How Lindian Resources Is Powering Up Kangankunde for 2026 Rare Earths Output

8:34am on Wednesday 8th of October, 2025 AEDT
Key Points
  • Early works program finished on schedule and budget
  • 5.5 km access road and security facilities operational
  • Owner-operator mining fleet procured for January 2026 mobilisation
  • Non-process infrastructure contracts underway alongside process plant design