First processing campaign of 49,082 tonnes completed on time and within budget
Mining schedule updated with a higher gold price assumption of $4,900/oz
Increased oxide ore mined in Campaign 1, with high-grade ore deferred to Campaign 2
Second processing campaign set to begin late December 2025