  • Joint development of modular data centre at Arrowsmith Production Facility
  • Initial 1 MW installation planned for early 2026, expanding to 4 MW by mid-year
  • Kala funds initial capital; Pilot issues shares upon successful commissioning
  • Potential expansion to 30-35 MW across Arrowsmith or Three Springs Solar project