Meteoric Resources Advances with Pilot Plant Wet Commissioning at Caldeira
8:47am on Tuesday 18th of November, 2025 AEDT
Key Points
Pilot plant construction and wet commissioning completed on schedule
Plant designed to process 25kg/hour of rare earth ore
Capital expenditure contained within A$1.5 million budget
First Mixed Rare Earth Carbonate production anticipated in early December