How Boab Metals Cut A$25M and Shaved 6 Months Off Sorby Hills Project
6:03pm on Wednesday 10th of December, 2025 AEDT
•
Mining
Read Story
How Boab Metals Cut A$25M and Shaved 6 Months Off Sorby Hills Project
6:03pm on Wednesday 10th of December, 2025 AEDT
Key Points
Minimum A$20 million savings from relocating and refurbishing DeGrussa Processing Plant
A$5 million reduction in Early Works capital expenditure through design and site efficiencies
Six-month reduction in construction timeline, enabling earlier revenue generation
Secured binding A$236 million debt facility supporting imminent Final Investment Decision