Vintage Energy revises its December 2025 quarterly report to highlight a conditional agreement to acquire Metgasco’s licence interests, while production dips amid ongoing operational efforts.
- Conditional agreement to acquire Metgasco and Bridgeport’s 25% stakes in Southern Flank JV
- Quarterly sales revenue declines 13% to $0.78 million due to lower gas production
- Divestment of 25% interest in PEP 171 completed for $1 million
- Cash position steady at $1.67 million with $10 million debt facility in place
- Ongoing dewatering and production uplift activities at Vali gas field
Southern Flank Joint Venture Reformation
Vintage Energy has updated its December 2025 quarterly report to include a key development in its Southern Flank Joint Venture (JV) strategy. The company signed a conditional agreement to acquire the 25% licence interests held by Metgasco Ltd, with plans to also acquire Bridgeport’s equivalent stakes. These moves, priced collectively at $5.9 million each, aim to consolidate Vintage’s control over the JV assets in the Cooper Basin, spanning South Australia and Queensland.
The acquisition is contingent on several conditions, including shareholder approval from Metgasco, which was secured in January 2026, Vintage securing funding commitments by late February, and completion of Bridgeport’s stake purchase by the end of March. Failure to meet these conditions could see the agreement terminated, underscoring the deal’s conditional nature.
Financial and Operational Performance
For the quarter ended 31 December 2025, Vintage Energy reported sales revenue of $0.78 million, down 13% from the previous quarter. This decline is primarily attributed to reduced gas production, which fell to 0.06 petajoules equivalent (PJe) from 0.08 PJe. Production challenges were linked to downtime in downstream infrastructure not operated by Vintage and ongoing dewatering efforts at the Vali gas field.
Despite the revenue dip, the company’s cash position remained stable at $1.67 million, supported by a $10 million debt facility from PURE Resources Fund. Net cash outflows from operating activities held steady at $0.57 million, with cost reductions in staff and administration partially offsetting lower cash receipts. The divestment of Vintage’s 25% interest in the Victorian exploration licence PEP 171 to Beach Energy Limited was completed during the quarter, generating $1 million in cash proceeds and allowing the company to focus resources on its Southern Flank operations.
Production Uplift and Field Operations
Vintage’s operational focus remains on its Production Uplift Program, particularly the dewatering and appraisal production from the Toolachee Formation at the Vali gas field. While gas flow has been established from wells Vali-2 and Vali-3, water production has not declined as expected, indicating potential formation damage or other reservoir challenges. The company is exploring mitigation strategies, including surfactant injection planned for the March quarter, to enhance gas flow and accelerate dewatering.
Meanwhile, the Odin gas field, operated jointly with Metgasco and Bridgeport, experienced reduced online days due to maintenance and infrastructure downtime, contributing to lower average daily gas production. Vintage is advancing geotechnical analysis for new well drilling within the Southern Flank permits, aiming to shift from appraisal to cash-generating production.
Looking Ahead
Vintage Energy is actively pursuing government grants under the South Australian Gas Incentive Grant Scheme to support drilling new appraisal wells. The company also plans to leverage its consolidated Southern Flank JV position to attract new joint venture partners, potentially enhancing operational scale and cash flow generation. While the company maintains confidence in its ability to continue operations with current cash flow levels, the success of these initiatives will be critical to reversing recent production declines and improving financial performance.
Bottom Line?
Vintage Energy’s Southern Flank JV consolidation and production uplift efforts set the stage for a pivotal 2026, but operational hurdles and funding conditions remain key watchpoints.
Questions in the middle?
- Will Vintage secure the necessary funding to complete the Southern Flank JV acquisitions on schedule?
- How effectively will the Production Uplift Program mitigate water production issues at the Vali gas field?
- What impact will government grant outcomes have on Vintage’s drilling and production plans?