Lindian Secures Key Equipment as Kangankunde Project Hits Major Construction Milestones

8:28am on Monday 9th of February, 2026 AEDT Mining
Read Story

Lindian Secures Key Equipment as Kangankunde Project Hits Major Construction Milestones

8:28am on Monday 9th of February, 2026 AEDT
Key Points
  • 200,000 lost-time injury-free hours achieved on site
  • Orders placed for SAG mill, thickener, floc plant, shaking tables, and belt filters
  • Owner-operated Komatsu mining fleet active, reducing reliance on contractors
  • Key milestones set, process plant construction and mine stripping in February, first blast in April, grid power energisation in July