Lindian Secures Key Equipment as Kangankunde Project Hits Major Construction Milestones
8:28am on Monday 9th of February, 2026 AEDT
•
Mining
Read Story
Lindian Secures Key Equipment as Kangankunde Project Hits Major Construction Milestones
8:28am on Monday 9th of February, 2026 AEDT
Key Points
200,000 lost-time injury-free hours achieved on site
Orders placed for SAG mill, thickener, floc plant, shaking tables, and belt filters
Owner-operated Komatsu mining fleet active, reducing reliance on contractors
Key milestones set, process plant construction and mine stripping in February, first blast in April, grid power energisation in July