Robex Hits Commercial Production at Kiniero with First Gold Shipment
8:58am on Thursday 12th of February, 2026 AEDT
•
Mining
Read Story
Robex Hits Commercial Production at Kiniero with First Gold Shipment
8:58am on Thursday 12th of February, 2026 AEDT
Key Points
First commercial gold shipment of approximately 197 kg (6,336 oz) dispatched
Kiniero processing plant achieved stable ramp-up with 393,000 tonnes processed in January
Metallurgical recovery averaged 88% with mill availability above 92%
Commercial production criteria met under Guinea Mining Code and Sprott financing