How Rox Resources Is Accelerating Youanmi Gold Production with Key Milestones

Rox Resources is advancing rapidly toward ore production at its Youanmi Gold Project, with underground mining progress, drilling programs underway, and critical plant construction contracts secured.

  • 750m underground advance at United North with mining rates increasing
  • Infill and resource growth drilling commenced to boost early mine inventory
  • Main pit dewatering progressing on schedule to expose portal positions
  • Interquip appointed as preferred EPC contractor with long-lead plant items ordered
  • Site infrastructure expanding to support mining and construction activities
An image related to ROX RESOURCES LIMITED
Image source middle. ©

Development Momentum at United North

Rox Resources Limited has reported significant progress at its 100%-owned Youanmi Gold Project in Western Australia, marking a clear step forward in its journey toward becoming one of the region’s next high-grade gold producers. Underground mining at the United North area is accelerating, with approximately 750 metres of development advance completed, including 512 metres in the decline. The company expects to reach the first level access by the end of February, a milestone that will open up initial ore production fronts.

Focused Drilling to Enhance Early Production

Complementing the underground development, Rox has initiated a surface infill drilling program targeting the upper levels of United North. Eleven holes have been completed so far, with assay results anticipated in the coming months. This drilling aims to close data gaps and increase confidence in the early years of production by identifying additional high-grade ounces. Plans are also underway to conduct underground diamond drilling to further define the first two years of mine production at a nominal 20m by 20m spacing.

Infrastructure and Plant Construction Advancements

On the infrastructure front, the company is expanding its site facilities to support both mining and construction activities. The camp capacity is being increased by 240 rooms in the first half of 2026, with an additional 120 permanent high-spec rooms ordered alongside new amenities such as a dry mess facility. Meanwhile, Rox has appointed Interquip as the preferred Engineering, Procurement, and Construction (EPC) contractor for the Youanmi Processing Plant. This engagement has already led to the ordering of key long-lead items including IsaMill ultra-fine grind mills, ball mills, crushers, and elution columns, aligning with the capital estimates from the Definitive Feasibility Study.

Dewatering and Exploration Progress

Dewatering of the Youanmi Main Pit remains on schedule, with discharge flowing to evaporation ponds and nearby pits. This work is critical to exposing historic decline portals and enabling further underground development. Exploration efforts continue beyond United North, with drilling planned at the Commonwealth-Connemarra and Hope prospects to delineate resources and generate new targets. Aeromagnetic surveys are also underway to map the greenstone belt’s geodynamic architecture, supporting a systematic pipeline of exploration targets over the next two years.

On Track for Final Investment Decision

Rox Resources remains on track to make its Final Investment Decision (FID) this quarter, supported by a $200 million placement and $18 million share purchase plan completed in late 2025. The company is actively progressing mine planning, contract awards, and approvals while working with debt advisors to secure project financing. With these developments, Rox is steadily advancing its pathway to production, aiming to transition from exploration and development to steady gold output in the near future.

Bottom Line?

Rox’s steady progress and strategic milestones position Youanmi as a compelling emerging gold producer to watch closely in 2026.

Questions in the middle?

  • What will the upcoming assay results reveal about the grade and extent of the United North resource?
  • How will Rox secure and structure project financing ahead of the Final Investment Decision?
  • What impact will regional exploration successes at Commonwealth-Connemarra and Hope have on the overall resource base?