Weather Delays Test Pacgold’s White Dam Production Ramp-Up Plans

Pacgold is set to enhance production at its White Dam Gold Project with the arrival of new screening and crushing equipment, aiming to ramp up heap leach throughput to 350 tonnes per hour. Assay and leach test results expected soon will clarify the production outlook for 2026-2027.

  • New Metso screen and cone crusher arriving at White Dam
  • Heap leach top lift re-crush to commence shortly
  • Production throughput target of approximately 350 tonnes per hour
  • Recent heavy rainfall caused minor site delays but leaching continues
  • Assay and LeachWELL test results imminent to guide production forecasts
An image related to Pacgold Limited
Image source middle. ©

Equipment Arrival Signals Production Step-Up

Pacgold Limited (ASX:PGO) is preparing to kick off a significant operational phase at its White Dam Gold Project in South Australia. The imminent arrival of a Metso ST 4.1 screen and HP300 cone crusher, along with a radial stacker, will enable the company to commence re-crushing the top lift of its existing heap leach pad. This move is designed to increase gold recovery efficiency and throughput, with a target of around 350 tonnes per hour once the circuit reaches full capacity.

Weather Challenges and Operational Resilience

Recent heavy rainfall, delivering approximately 100mm of rain, temporarily restricted site access and paused some refurbishment work on the carbon-in-column (CIC) tanks. Despite this, leaching operations have continued, and the additional water has been welcomed for irrigation purposes. Pacgold’s management emphasises that safety remains paramount, and while the weather caused a short delay, the site is on track to resume full operations shortly.

Assays and Test Work to Inform Future Production

Alongside the equipment mobilisation, Pacgold anticipates receiving assay results from sampling the heap leach’s top lift and outcomes from LeachWELL test work within the coming weeks. These results are critical as they will allow the company to refine its production forecasts for the 2026-2027 period, providing investors with clearer visibility on expected gold output and revenue generation.

Strategic Positioning and Growth Prospects

The White Dam Gold Project, located 80km east of Broken Hill, represents a cornerstone asset for Pacgold’s transition from explorer to producer. The acquisition of this operational gold extraction facility offers a near-term pathway to cash flow, supporting ongoing exploration efforts at other promising projects such as the Alice River Gold Project in Queensland. The re-crush initiative at White Dam is a tangible step towards unlocking additional value from existing resources.

Looking Ahead

As Pacgold ramps up its heap leach operations with new equipment and awaits critical assay data, the company is poised to deliver on its production potential. The coming months will be pivotal in confirming the scale and timing of output increases, setting the stage for Pacgold’s next growth chapter.

Bottom Line?

Pacgold’s heap leach re-crush marks a key operational milestone, with upcoming assay results set to shape its production trajectory.

Questions in the middle?

  • What will the assay and LeachWELL test results reveal about remaining gold resources?
  • How quickly can Pacgold ramp up to the targeted 350 tonnes per hour throughput?
  • What impact will recent weather delays have on the overall production schedule?