Ausgold Advances Katanning Workforce Village with $30.1m EPC Contract

8:12pm on Friday 15th of May, 2026 AEST Mining
Read Story

Ausgold Advances Katanning Workforce Village with $30.1m EPC Contract

8:12pm on Friday 15th of May, 2026 AEST
Key Points
  • EPC contract signed with ADD for 250-room accommodation village
  • Construction to start May 2026, partial availability by mid-September
  • Total cost estimated at $30.1 million, slightly above DFS estimate
  • Village completion aligns with key permits and Q4 2026 final investment decision