Bendigo-Ophir Gold Project Enters Fast-track Hearing Stage with October Decision Set

Mining By Maxwell Dee 2 min read

Santana Minerals' Bendigo-Ophir Gold Project has entered the hearing phase of its regulatory assessment, with concurrent technical hearings scheduled for June and a statutory decision due by late October 2026.

  • BOGP progresses to hearing phase under Fast-track Approvals Act
  • Concurrent technical hearings across multiple disciplines set for June
  • Further technical information and management plan refinements requested
  • Updated plans due to Expert Panel by 22 June 2026
  • Statutory decision expected by 29 October 2026

BOGP Moves Into Advanced Regulatory Assessment Stage

Santana Minerals (ASX:SMI) has announced a significant milestone in its Bendigo-Ophir Gold Project (BOGP) journey, with the project now entering the hearing phase under New Zealand’s Fast-track Approvals Act. This stage involves a series of concurrent technical hearings scheduled for June 2026, marking a critical step in the project’s regulatory scrutiny ahead of the statutory decision deadline on 29 October 2026.

Expert Panel Demands Further Technical Detail and Management Refinements

The Expert Panel overseeing the assessment process has requested additional technical information and refinements to the project’s management plans and consent conditions. Particular attention is being paid to groundwater management, an area often pivotal in mining approvals. Santana Minerals is preparing to submit updated management frameworks and proposed conditions by 22 June 2026, adhering to the assessment timetable.

Assessment Process Reflects Normal Rigour of Major Project Approvals

Damian Spring, Executive Director and CEO, emphasised that the requests for clarification and differing technical opinions are standard features of major project assessments. He noted that these steps are part of the Panel’s process to rigorously test evidence and inform its final decision. Importantly, Spring reaffirmed that Santana Minerals’ development plans remain on track and are expected to deliver substantial economic benefits to New Zealand, aligning with the Fast-track Approvals Act’s purpose.

Regulatory Timeline Provides Clarity Amid Project Progress

The statutory decision date remains firmly set for 29 October 2026, with a draft decision anticipated at least six weeks prior. This timeline offers a clear regulatory framework for the project’s next phases, which include finalising management plans and securing consent conditions. The progression to hearings follows earlier developments, including capital raises and land settlement clarifications, which have underpinned the project’s advancement towards construction.

Bottom Line?

The upcoming submission of revised management plans and the June hearings will be pivotal moments in determining whether the BOGP can maintain its development momentum towards late 2026 construction.

Questions in the middle?

  • How will the Expert Panel’s feedback on groundwater management influence final consent conditions?
  • Could ongoing technical disagreements delay the statutory decision beyond October 2026?
  • What economic benefits does Santana Minerals anticipate if approvals proceed as planned?