Savannah Goldfields Advances Toward Agate Creek Mining Restart with Environmental Nod Pending
Savannah Goldfields is edging closer to resuming mining at its Agate Creek project, awaiting a key environmental approval expected by mid-July. Early site works are underway, while gold production continues from alternative sources at the Georgetown plant.
- Environmental Authority decision expected by 13 July 2026
- Early site preparations underway under existing permits
- Agate Creek Ore Reserves total 460,000 tonnes at 2.5 g/t Au
- 375,000 tonnes scheduled for mining through 2028
- Georgetown plant holds over 50 days of feedstock
Environmental Approval Delayed but Nearing Decision
Savannah Goldfields Limited (ASX:SVG) is on the cusp of restarting mining at its Agate Creek Gold Project in Far North Queensland, pending a final Environmental Authority from the Department of Environment, Tourism, Science and Innovation (DETSI). The company received a preliminary draft of the updated Environmental Authority on 29 May 2026, but DETSI extended the decision period by 30 business days, pushing the expected approval date to 13 July 2026.
This extension follows a change application lodged in November 2025, which updates pit designs and waste rock management plans. Savannah has maintained constructive dialogue with DETSI over the past nine months, and CEO Brad Sampson expressed optimism about finalising the conditions during this extended review.
Early Works Signal Readiness to Restart Mining
Despite awaiting formal approval, Savannah has commenced early site works at Agate Creek under existing authorisations. Preparations include haul road stabilisation, erosion and sediment control, water management features, and refurbishing camp and site facilities. These steps aim to enable a swift transition to full-scale mining immediately after receiving the Environmental Authority.
Ore Reserves and Production Schedule
The Agate Creek Ore Reserves comprise 460,000 tonnes at an average grade of 2.5 grams per tonne gold, containing approximately 36,800 ounces of gold. Savannah plans to mine an initial 375,000 tonnes at a slightly higher grade of 2.65 g/t Au, equating to 31,900 ounces, over the remainder of 2026, through 2027, and into 2028. This ore will be trucked to the company's Georgetown Gold Processing Plant (GGPP) for processing.
Georgetown Plant Operations and Feedstock Management
The Georgetown plant is currently running at around 550 tonnes per day, supported by over 50 days of feedstock stockpiled on site. These stocks mainly consist of 28,500 tonnes of Big Ben material at an estimated 1.4 g/t Au and 1,500 tonnes of Big Reef material at about 2.9 g/t Au. Additionally, 13,500 tonnes of Big Reef ore are in the process of being mined and transported to the plant. Savannah is assessing opportunities to supplement feedstock further from Big Reef and Big Ben to maintain continuous production ahead of Agate Creek ore arrival.
Balancing Production While Awaiting Approval
While the Agate Creek Environmental Authority decision remains pending, Savannah continues gold production from alternative sources to sustain operations at the Georgetown plant. This approach ensures ongoing cash flow and operational momentum as the company prepares for the mining restart. The company’s strategy reflects a cautious but proactive stance, aligning with regulatory timelines and operational readiness.
Bottom Line?
Savannah Goldfields is poised to resume Agate Creek mining pending mid-July environmental approval, with early site works and ongoing Georgetown production cushioning the wait.
Questions in the middle?
- Will DETSI’s extended review impose new conditions that could delay mining restart further?
- Can Savannah secure additional feed sources to extend Georgetown plant operations before Agate Creek ore arrives?
- How will the planned mining schedule at Agate Creek impact Savannah’s overall production profile through 2028?