Lindian Advances Kangankunde Toward Q4 2026 Production
8:16am on Monday 22nd of June, 2026 AEST
•
Mining
Read Story
Lindian Advances Kangankunde Toward Q4 2026 Production
8:16am on Monday 22nd of June, 2026 AEST
Key Points
Over 800,000 LTI-free work hours with 3,318 workers onsite
First blast drilling underway, haul road and explosives approvals secured
Tailings storage and power infrastructure 50% and fully complete respectively
27,000 tonnes of ore stockpiled to support commissioning