Lindian Advances Kangankunde Toward Q4 2026 Production

8:16am on Monday 22nd of June, 2026 AEST Mining
Read Story

Lindian Advances Kangankunde Toward Q4 2026 Production

8:16am on Monday 22nd of June, 2026 AEST
Key Points
  • Over 800,000 LTI-free work hours with 3,318 workers onsite
  • First blast drilling underway, haul road and explosives approvals secured
  • Tailings storage and power infrastructure 50% and fully complete respectively
  • 27,000 tonnes of ore stockpiled to support commissioning