Eloise produced 2,683 tonnes payable copper at AISC $6.15/lb
Jericho ore processing started, contributing 304 tonnes copper
Eloise expansion 81% complete, commissioning on track for Dec 2026
FY26 copper production met guidance with strong cash flow