Aurum Resources Unveils $1.5B NPV Boundiali Gold Project with Maiden Ore Reserve

8:54am on Tuesday 28th of July, 2026 AEST Mining
Read Story

Aurum Resources Unveils $1.5B NPV Boundiali Gold Project with Maiden Ore Reserve

8:54am on Tuesday 28th of July, 2026 AEST
Key Points
  • Maiden Probable Ore Reserve of 42.1 Mt at 0.9 g/t Au for 1.21Moz gold
  • Pre-Feasibility Study shows post-tax NPV5% of US$1.5 billion and IRR of 119%
  • 11-year mine life with payback under one year post-tax from first production
  • Environmental approvals secured; Definitive Feasibility Study underway targeting late 2026 FID