Elevate Uranium Boosts Marenica Resource 31% and Targets August Pilot Plant Results

Elevate Uranium continues refining its U-pgradeTM Pilot Plant with results expected in August 2026, while boosting its Marenica Uranium Project ownership to 90% and expanding the resource by 31%.

  • U-pgradeTM Pilot Plant optimisation ongoing with August results targeted
  • Marenica Uranium Project ownership increased to 90%
  • Mineral resource at Marenica grows 31% to 52.8 Mlb U3O8
  • Exploration expenditure totals $4.1 million, cash reserves at $28.9 million
  • Procurement and customs delays impact pilot plant timeline
An image related to Elevate Uranium Ltd
Image © middle. Logo © respective owner.

Pilot Plant Progress and Operational Challenges

Elevate Uranium Ltd (ASX:EL8) is pushing forward with its U-pgradeTM Pilot Plant in Namibia, aiming to validate its proprietary beneficiation process that concentrates uranium and rejects waste material. The company expects to release pilot plant results in August 2026, though this timeline is tentative due to ongoing delays.

The delays stem primarily from extended procurement and customs clearance issues, aggravated by Namibia's transition to an upgraded electronic customs system. Elevate has bolstered its in-country technical team with additional metallurgists and realigned personnel to improve operational efficiency. Managing Director Murray Hill has also been heavily involved onsite, providing direct technical support to accelerate progress.

Despite these setbacks, Elevate confirms that its previously announced bench-scale testwork remains valid and unaffected by the pilot plant's operational delays. The company is fully funded and committed to delivering high-quality data to support future technical studies and commercialisation of the U-pgradeTM process.

Ownership Consolidation and Resource Expansion at Marenica

In a strategic move, Elevate has increased its stake in the Marenica Uranium Project to 90% by entering agreements to acquire shares from other shareholders. This simplified ownership structure is expected to be finalised by the end of July 2026, enhancing Elevate’s economic and strategic control over the project and aligning shareholder value.

Alongside ownership consolidation, the Marenica resource estimate has been significantly upgraded. The JORC 2012 Mineral Resource Estimate (MRE) now stands at 52.8 million pounds of U3O8 at a 100 ppm cut-off grade, marking a 31% increase. Infill drilling to convert inferred resources to indicated categories is underway and expected to continue into early August 2026, supporting advancing pre-development programs.

Broader Resource Portfolio and Financial Position

Elevate’s Namibian portfolio, including the Koppies Uranium Project and other tenements, holds substantial uranium resources, with the Koppies project alone containing 76.2 Mlb U3O8. In Australia, the company maintains interests in several projects and joint ventures, collectively adding approximately 57 Mlb of high-grade uranium resources.

Financially, Elevate reported exploration expenditure of $4.1 million for the quarter and ended June 2026 with cash holdings of $28.9 million. Payments to related parties, including directors’ fees and salaries, amounted to approximately $210,000 during the quarter. The company remains well-capitalised to continue its exploration and development activities.

Tenement Status and Regulatory Considerations

Several Namibian mineral licences are pending renewal or awaiting environmental clearance certificates, a process that can extend beyond licence expiry and involves multiple regulatory layers. Elevate continues to manage these administrative processes alongside its operational activities. In Australia, all tenements are granted or under application, with expiry dates ranging up to 2031.

The company’s ongoing efforts to optimise the U-pgradeTM Pilot Plant and advance its resource base come amid these regulatory and logistical complexities, underscoring the challenges of developing uranium projects in multiple jurisdictions.

Bottom Line?

As Elevate Uranium navigates operational delays and regulatory hurdles, the pending pilot plant results and ownership consolidation at Marenica will be pivotal milestones shaping its next phase of development.

Questions in the middle?

  • Will the U-pgradeTM Pilot Plant overcome procurement and customs delays to deliver timely results?
  • How will the increased 90% ownership impact Elevate’s strategic decisions and project economics at Marenica?
  • What are the implications of ongoing infill drilling for upgrading resource classifications and advancing feasibility?