Maritana Minerals Advances Black Swan Hub with Early Works and Approvals on Track
Maritana Minerals is steadily progressing its Black Swan Processing Hub project, with demolition, earthworks, and procurement well underway, aiming for first gold production in the second half of 2027.
- Early works ramp up with demolition and earthworks
- Clearing Permit nearing final approval
- Construction camp expanded to support workforce
- Long-lead equipment procurement advancing
- Project remains on track for H2 2027 gold output
Steady Progress on Physical Execution
Maritana Minerals (ASX:MRT) is transitioning the Black Swan Processing Hub (BSPH) project from approvals to active site work, with GR Engineering Services mobilised and demolition, earthworks, and detailed engineering well underway. The company has commenced removing redundant conveyors and structures while refurbishing sound plant sections, setting the stage for mill refurbishment and new infrastructure installation.
Approvals Advancing with Key Permits in Final Stages
The regulatory pathway remains on course, with the Mine Development Closure Plan and Works Approval milestones already secured. The critical Clearing Permit for the Carbon in Leach (CIL) earthworks is progressing through its final approval process, a necessary step before earthworks can fully advance.
Infrastructure and Earthworks Accelerate
Bulk earthworks have been awarded, covering the Run of Mine (ROM) pad, CIL circuit, and supporting infrastructure. Select fill material deliveries for CIL tank foundations have started, indicating tangible progress on site preparation. Concurrently, Flow Water Services is refurbishing and upgrading the borefield to supply construction water, including installing pumps, piping, and communications gear.
Accommodation Expansion Supports Workforce Growth
The construction camp has expanded significantly, with a second stage adding 57 rooms now complete and operational since early August. A permanent 60-room camp contract has been awarded, with modules like the kitchen ordered and expected to be ready by November 2026. Additional amenities such as wet and dry mess facilities, laundry, BBQ, and gym are already installed, supporting the growing onsite workforce.
Long-Lead Procurement and Engineering Parallel
Procurement of critical long-lead equipment, including the pre-leach thickener and replacement SAG and ball mill motors, continues alongside detailed engineering. This parallel approach aims to protect the development schedule and keep the project on track for the targeted first gold production in H2 CY2027.
Bottom Line?
Maritana’s disciplined execution and parallel procurement efforts position the Black Swan Processing Hub well for its 2027 production target, though final permit approvals and construction milestones warrant close monitoring.
Questions in the middle?
- Will the Clearing Permit for the CIL earthworks be granted without delay?
- How will ongoing procurement and engineering challenges impact the H2 2027 production timeline?
- What are the potential risks around construction water supply and infrastructure readiness?