GenusPlus adds major wind farm connection work through 2028

Infrastructure By Nora Hopper 2 min read

GenusPlus Group has secured an approximately $135 million design and construct contract for the grid connection of Atmos Renewables’ 470MW Parron Maam Marang Farm in Western Australia. The award offers work through 2028, although the main construction phase remains conditional on project milestones including financial close and a Notice to Proceed.

  • Approximately $135 million contract including preliminary early works
  • 330kV terminal, transmission lines and ancillary infrastructure
  • Supports Atmos Renewables’ 470MW Parron Maam Marang Farm
  • Construction scheduled for completion in 2028
  • Main works conditional on financial close, connection agreements and Notice to Proceed

GenusPlus Group Ltd (ASX:GNP) has won an approximately $135 million contract to build the high-voltage connection for a 470MW wind farm in Western Australia, extending its pipeline of energy infrastructure work into 2028.

The Design and Construct contract from Atmos Renewables covers a 330kV terminal, 330kV transmission lines and associated ancillary works at the Parron Maam Marang Farm Substation near Badgingarra. GenusPlus has already undertaken preliminary activity on the project, including detailed design, procurement of long-lead items and bulk earthworks, and the stated contract value includes those early works.

Construction remains subject to project milestones

The headline value is not yet a guarantee that the full construction package will proceed. GenusPlus said construction is subject to customary conditions precedent, including Atmos Renewables reaching financial close, executing connection agreements and issuing a Notice to Proceed.

That qualification matters for the timing of revenue and workload. The company did not disclose expected margins, payment terms or the contract’s contribution to earnings, so the announcement establishes the scale of the award more clearly than its financial profile.

Parron Maam Marang targets 2028 completion

The project is supported by the Federal Government’s Capacity Investment Scheme as Western Australia prepares to exit coal-fired power by 2030. GenusPlus Managing Director David Riches said the contract builds on the company’s relationship with Atmos, which also includes work on the Merredin BESS Project.

For GenusPlus, the immediate question is whether the remaining project approvals convert the award into sustained construction activity. Financial close, connection agreements and the Notice to Proceed are the next concrete markers, while completion of the works is scheduled for 2028.

Bottom Line?

The contract adds meaningful visibility through 2028, but its ultimate earnings impact depends on financial close and the release of the construction phase.

Questions in the middle?

  • When will Atmos Renewables achieve financial close and issue the Notice to Proceed?
  • How much of the approximately $135 million value remains to be recognised after early works already completed?
  • What margins and revenue timing will GenusPlus disclose once construction formally begins?