Cyprium brings dormant Nifty copper complex to the brink of first cathode
9:05am on Wednesday 30th of September, 2026 AEST
•
Mining
Read Story
Cyprium brings dormant Nifty copper complex to the brink of first cathode
9:05am on Wednesday 30th of September, 2026 AEST
Key Points
First cathode production expected in the December quarter of 2026
Production wellfield expanded to 98 wells accessing about 1.7 million tonnes of leachable material
Phase 1 targets approximately 6,000 tonnes per annum of cathode capacity
FY2026 net loss narrowed to A$15.6 million from A$26.4 million