EcoGraf outlines bigger Epanko graphite opportunity with lower unit costs
2:04pm on Friday 2nd of October, 2026 AEST
•
Mining
Read Story
EcoGraf outlines bigger Epanko graphite opportunity with lower unit costs
2:04pm on Friday 2nd of October, 2026 AEST
Key Points
Potential Stage 1 production increase to 87,600tpa during the Oxide phase
First-10-year C1 costs estimated at US$512.3/t, down 5.8%
Initial capital rises by US$12 million to US$193.2 million
The existing 73,000tpa case remains the development and debt-financing basis