Toubani’s Kobada build reaches CIL tank milestone ahead of first gold

9:36am on Tuesday 6th of October, 2026 AEDT • Mining
Read Story

Toubani’s Kobada build reaches CIL tank milestone ahead of first gold

9:36am on Tuesday 6th of October, 2026 AEDT
Key Points
  • CIL tank erection has commenced at Kobada
  • More than 70% of project costs are committed
  • Process plant engineering is over 95% complete and long-lead equipment has shipped
  • About US$50 million of the US$160 million stream facility has been drawn