West Wits funding clears another hurdle as Qala Shallows advances toward production

10:44am on Wednesday 7th of October, 2026 AEDT • Mining
Read Story

West Wits funding clears another hurdle as Qala Shallows advances toward production

10:44am on Wednesday 7th of October, 2026 AEDT
Key Points
  • R236 million second drawdown received under the R875 million Absa and Nedbank senior facility
  • Underground development reached 1,150 metres by September, with September advance rising to 200 metres
  • Stoping is scheduled to begin in February 2027, ahead of commercial production targeted for Q4 2027
  • Surface infrastructure was 61% complete at September, while permanent backup power is due for commissioning in October