Home › Water Technology and Mining Services › Clean Teq Water (ASX:CNQ)

Clean TeQ’s cash milestone puts recurring revenue under the microscope

Water Technology and Mining Services By Victor Sage 4 min read

Clean TeQ Water reported positive operating cash flow and a 60% quarterly rise in customer receipts as its project portfolio moved deeper into delivery. The quarter also brought progress on major lithium, wastewater and scandium projects, but the next test is converting those milestones into durable earnings.

  • Customer receipts rose 60% quarter-on-quarter to A$10.2 million
  • Positive operating cash flow of A$0.75 million
  • Cash increased to A$9.2 million at 30 September
  • First long-term ATA polymer supply and technology licence secured
  • Rincon, Balen and Syerston projects advanced

Cash generation improves as projects reach delivery milestones

Clean TeQ Water Limited (ASX:CNQ) began FY27 with something its project-heavy business has been working towards: positive operating cash flow. Customer receipts reached A$10.2 million in the September quarter, up 60% from A$6.4 million in the previous quarter, while net operating cash inflow was A$0.75 million.

Cash and cash equivalents rose from A$8.7 million at 30 June to A$9.2 million at 30 September, despite A$0.17 million of net financing outflows and a A$0.06 million foreign exchange impact. The figures describe cash movement rather than quarterly profit or revenue, but they provide a useful measure of whether Clean TeQ is funding its expansion without an immediate equity injection.

Rasp Mine agreement gives ATA a recurring revenue foothold

The most strategically important development was the long-term polymer supply and technology licence agreement for the Rasp Mine in Broken Hill. The arrangement covers ATA polymer reagents and licensing, with an initial five-year term from commissioning that can be extended by Broken Hill Operations to as much as 20 years. Revenue will vary with the volume of tailings processed, although the company has not disclosed the expected dollar contribution.

The agreement builds on the Rasp Mine ATA contract, which covered the design and construction of the tailings dewatering plant. Clean TeQ said detailed design and HAZOP work are complete, long-lead equipment is on order and practical completion remains targeted for the third quarter of FY27. The commercial question now shifts from securing the arrangement to commissioning the plant and establishing the volume of tailings that will generate reagent and licence income.

Rincon and Balen remain the main execution tests

Clean TeQ’s US$12.5 million CLEAN-IX contract for Rio Tinto’s Rincon lithium project in Argentina was 78% complete in September. Detailed design, major equipment procurement and resin manufacture were complete, fabrication was advancing, and Rio Tinto had approved an extension of time taking the delivery date to 4 December 2026.

At Nyrstar’s Balen operations in Belgium, the A$10.4 million Phase 2 DESALX wastewater project moved from 21% to 47% complete during the quarter. Major subcontracts have been placed and equipment fabrication is progressing, with commissioning targeted for August 2027. These projects offer evidence of a substantial order book, but they also leave execution, delivery and commissioning as important determinants of future cash conversion.

Commercial references expand across water and critical minerals

In Ireland, the €7 million PHOSPHIX phosphate removal plant delivered with Enva reached completion in July, on schedule and within budget. Performance testing recorded phosphate below 0.1 milligrams per litre against a contractual requirement of 1.0 milligram per litre, while hydraulic throughput also exceeded the contracted level. The plant is now in its defects liability period, and Clean TeQ has received its first operational spares order, following the PHOSPHIX European debut.

Sunrise Energy Metals also awarded Clean TeQ FEED and Early Works of up to A$5.4 million for the Syerston Scandium Project, covering an MBIX-based ion exchange circuit and scandium oxide refinery. The work supports Sunrise’s investment readiness, but the timing of a final investment decision remains with Sunrise. Engineering and testwork are also under way for Aura Energy’s Tiris uranium project, while Arafura rare earths separation piloting has begun in Melbourne.

Bottom Line?

Clean TeQ has entered FY27 with better cash conversion and a signed annuity-style agreement, but the investment case now depends on commissioning Rasp, delivering Rincon and turning feasibility-stage critical minerals work into funded projects.

Questions in the middle?

  • What level of reagent and licence income will the Rasp Mine agreement generate once commissioning begins?
  • Can Clean TeQ deliver Rincon by the revised December 2026 date while keeping cash conversion positive?
  • Will Sunrise Energy Metals progress Syerston from FEED and Early Works to a final investment decision?