Arafura turns Nolans into a construction project with A$885 million in reserves

Mining By Maxwell Dee 5 min read

Arafura Rare Earths has moved its Nolans rare earths project from financing decision to early construction, with A$700 million of procurement scope advanced during the September quarter. The company ended the period with A$885 million in cash and term deposits, while major debt and equity funding arrangements remain subject to completion conditions.

  • Early site access, mobilisation and the first construction contract commenced
  • Approximately A$700 million of procurement scope advanced, with a further A$350 million of tenders expected within six months
  • A$885 million held in cash and term deposits at 30 September 2026
  • 500-tonne-per-year wind turbine offtake extended on seaborne index-linked pricing
  • Project debt and approximately A$230 million of cornerstone equity remain subject to contractual close and conditions precedent

Nolans moves from final investment decision to early construction

Arafura Rare Earths Limited (ASX:ARU) has begun the physical transition from project approval to project delivery at Nolans, commencing early site access and mobilisation works during the September quarter. The company had taken its final investment decision in May, and now says the owner’s team and Hatch, its engineering, procurement and construction management contractor, have been ramped up for execution.

“Images: (Left to right, prior page and above) Fly camp and main camp, site access road, hardstand, site access roads.”Caption and image © Arafura Rare Earths Ltd. From “Quarterly Activities/Appendix 5B Cash Flow Report”, 30 Oct 2026.

The first construction contract has been awarded, while site reinstatement and accommodation-readiness works progressed. Permanent access from the Stuart Highway is being prepared ahead of major construction, with the company describing the intersection as critical to public safety and the movement of machinery and equipment. Bulk earthworks, hardstand preparation and further mobilisation activities began after quarter end. The project reported a Total Recordable Injury Frequency Rate of 0.00 for the period.

A$700 million procurement pipeline advances

Procurement work equivalent to approximately A$700 million of scope was completed during the quarter, including packages committed, tendered or issued to market. About 70 packages were uploaded through the Industry Capability Network Gateway, although most of that procurement remains under assessment rather than awarded. Arafura expects to put a further A$350 million of tenders to market over the next six months.

The scale of the work marks a meaningful step beyond the Nolans final investment decision, which was reported alongside more than A$700 million in cash and term deposits and a planned September construction start. It also creates a new execution test: the next phase will depend less on announcements of intent and more on package awards, engineering maturity and construction progress.

Offtake pricing shifts towards an external index

On 18 September, Arafura extended its existing agreement with a global wind turbine manufacturer for 500 tonnes per annum of neodymium-praseodymium oxide. The revised pricing terms are linked to an independent seaborne price index, a move that aligns with the company’s stated aim of using a transparent global benchmark. The 500-tonne wind turbine offtake was previously reported as a five-year agreement with a possible extension, but the filing does not disclose its financial value.

After quarter end, Arafura also announced a binding five-year agreement with a US trading group and named participant in the Project Vault initiative, with volumes ramping to 850 tonnes per annum once Nolans reaches nameplate production. The company says discussions continue over the remaining modest volume of NdPr available, including the 500 tonnes earmarked under the Australian Government’s Critical Minerals Strategic Reserve. It will generally withhold counterparty identities unless they are themselves material.

Cash rises while project financing remains unfinished

Arafura reported A$160 million in cash and cash equivalents plus A$725 million in term deposits at 30 September, giving total cash and term deposits of A$885 million. The figure compares with A$723 million at 30 June according to the report’s headline disclosure, although a later sentence in the filing appears to reverse those dates. During the quarter, Arafura placed A$225 million into term deposits and recorded A$181.0 million of net financing inflows, largely reflecting equity proceeds and associated transaction costs.

Cash used in operating activities was A$14.3 million, while project development payments totalled A$14.8 million. The Appendix 5B calculates 11 quarters of funding based on cash and the quarter’s relevant outgoings, but that measure does not represent the full cost of building Nolans. Debt facilities backed by export credit agencies and commercial lenders remain subject to final credit approvals and contractual close. The approximately A$230 million of cornerstone equity subscriptions from the German Raw Material Fund and Export Finance Australia are likewise still subject to conditions precedent, with completion expected alongside the debt close.

Environmental approvals and process improvements continue

Work on the Environmental Mining Licence framework continued through risk assessments, environmental outcomes, site-layout refinement and securities planning. Arafura also completed the first tranche of its lender-agreed Environmental and Social Action Plan, with contractual close corrective actions signed off by Tetra Tech Coffey.

Engineering is advancing across the extraction and separation plants, including studies aimed at improving dysprosium and terbium recovery from acid purification waste liquor. Pilot testing with Clean TeQ on ion-exchange separation is expected to run through the end of the calendar year. At the board level, Ian Murray became chair after Mark Southey’s resignation following the 22 October annual meeting, adding a leadership change to a quarter otherwise defined by the shift into execution.

Bottom Line?

The next value-defining milestones are likely to be procurement awards, contractual close on debt and cornerstone equity, and evidence that early works are converting into major construction without new funding or approval friction.

Questions in the middle?

  • When will the debt facilities and EFA and German Raw Material Fund equity subscriptions reach contractual close?
  • How much of the A$700 million procurement pipeline will be awarded, and on what commercial terms?
  • Can the Environmental Mining Licence framework and Clean TeQ pilot work progress without disrupting the construction schedule?