middle.news

Hastings turns Thai plant stake into a 2027 production test

5:46pm on Friday 30th of October, 2026 AEDT • Mining and critical minerals
Read Story

Hastings turns Thai plant stake into a 2027 production test

5:46pm on Friday 30th of October, 2026 AEDT
Key Points
  • 49% Kabin Buri plant acquisition completed for consideration capped at US$15 million
  • First Thai MREC production targeted for Q2 CY2027 at approximately 12,000 tonnes per annum
  • Yangibana Stage 1 DFS shows A$649 million pre-tax NPV and 34% IRR
  • Yangibana requires approximately A$333.4 million of initial capital before FID
Read Story
middle.

Tap to Read

Tap the card to read the full analysis
about Hastings Technology Metals (ASX:HAS)
OPEN ARTICLE