Macro Metals puts BHP delivery and Yandi South at the centre of its next growth phase
7:20pm on Friday 30th of October, 2026 AEDT
•
Mining
Read Story
Macro Metals puts BHP delivery and Yandi South at the centre of its next growth phase
7:20pm on Friday 30th of October, 2026 AEDT
Key Points
A$2.8 million of unaudited services work performed, up from A$2.004 million
BHP’s A$12.52 million Mt Goldsworthy work package 28.1% complete and ahead of schedule
Yandi South acquisition completed after quarter end, with nine new prospects identified
A$3.28 million placement and proposed chairman’s loan conversion announced in October