Latrobe Magnesium advances plant commissioning toward first metal

Latrobe Magnesium has lifted commissioning progress at its Victorian Phase 1B plant to 50%, with installation now 98% complete. The company continues to target first magnesium metal crowns exceeding 98% purity by the end of 2026, while remaining within its A$6.1 million project budget.

  • Phase 1B installation reaches 98% completion
  • Commissioning doubles to 50% from 25% in September
  • First magnesium metal remains targeted for end-2026
  • All reagent supplies are on site
  • Project forecast remains within the A$6.1 million budget
An image related to Latrobe Magnesium Limited Add us as a preferred source on Google
Image © middle. Logo © respective owner.

Commissioning reaches the halfway mark

Latrobe Magnesium Limited (ASX:LMG) has moved its Latrobe Valley demonstration plant deeper into the critical commissioning phase, reporting that 50% of Phase 1B commissioning was complete at 31 October, up from 25% a month earlier. Installation is now 98% complete, leaving only minor works that the company says do not affect the commissioning critical path.

Reduction Furnace electrical QA/QC final checks
Image © Latrobe Magnesium Limited. From “October Project Update”, 2 Nov 2026.

The project remains aimed at producing magnesium metal crowns containing more than 98% magnesium by the end of 2026. That target is still forward-looking, but the latest update puts the plant materially closer to the technical milestone than it was in September. The previous Phase 1B commissioning update had reported the plant at 35% commissioned and 95% installed.

Reduction Furnace moves into testing

Work is now concentrated on turning installed equipment into an operating plant. Commissioning of the Reduction Furnace began in late October, with vendor representatives on site for system testing. Vacuum testing has been completed across all 30 retort and condenser assemblies, and those assemblies have been delivered to the site.

Reduction Furnace electrical QA/QC final checks
Caption and image © Latrobe Magnesium Limited. From “October Project Update”, 2 Nov 2026.
Successfully loading charge into Ball Mill
Image © Latrobe Magnesium Limited. From “October Project Update”, 2 Nov 2026.
Caption and image © Latrobe Magnesium Limited. From “October Project Update”, 2 Nov 2026.

In the Briquetting area, the Ball Mill has been charged and reagent ore commissioning and control-system tuning have started. Mechanical and electrical testing of the Crown Handling Baler is complete, while testing of the automatic load shuttle, utilities and SCADA controls continues. All reagent supplies required ahead of first metal production are reported to be on site.

Budget holds as final works continue

Latrobe says the project forecast remains within its original A$6.1 million budget, with forecast cash spending in line with the A$3.8 million allocated in its recent equity raising. The company had completed a A$3.4 million entitlement offer shortly before this update, with the earlier funding announcement saying the raise was intended to carry the Victorian demonstration plant towards targeted first production.

Remaining work includes minor grouting in the Reduction Furnace area, installation of roof components and upper expansion joints, final fire-monitoring systems and further commissioning checks. Latrobe says these activities are expected to progress in the coming weeks as the plant transitions from installation into operations.

Safety record remains intact

Health and safety performance has remained strong during the more demanding commissioning phase. Weekly HSE audit compliance stayed above 98% throughout October, and the project has recorded zero recordable incidents since commencement.

The next hard evidence will come from furnace and retort performance rather than installation percentages. Latrobe’s end-of-year first-metal target now depends on completing those tests, moving through the remaining commissioning stages and demonstrating that the system can produce the promised magnesium purity within the stated timeframe.

Get ASX:LMG news the moment it breaks

Instant push notifications No waitlist Free
Download on the App Store iPhone & iPad
Get it on Google Play Android
Email alerts

Bottom Line?

Installation is nearly finished, but the investment case now turns on whether furnace commissioning converts progress on paper into first metal before year-end.

Questions in the middle?

  • Can the Reduction Furnace and retort systems complete commissioning without shifting the end-2026 first-metal target?
  • Will final project spending remain within the A$6.1 million budget as commissioning intensifies?
  • What operating performance and magnesium purity will the first metal crowns demonstrate?