Pacific Lime secures A$50m backing as DFC advances PNG industrial platform
Pacific Lime and Cement has secured firm commitments for a A$50 million placement while advancing a proposed US$15 million convertible note with the United States International Development Finance Corporation. The funding is aimed at moving its Papua New Guinea lime, cement, port and industrial precinct projects towards construction and commercialisation.
- A$50 million placement at A$0.36 per CDI, representing 14.9% of existing shares
- Proposed US$15 million DFC convertible note remains subject to due diligence and definitive documents
- Central Lime production remains targeted for late Q1 to Q2 CY2027
- A$27 million allocated to SEZ precinct and port expansion development
- Central Cement Project early works and pre-FID spending receive A$10 million
Add us as a preferred source on Google
A$50 million placement funds the next construction phase
Pacific Lime and Cement Limited (ASX:PLA; PNGX:PLC) has secured the immediate capital it needs to push its Kido/Rearea industrial platform forward, with firm commitments for a A$50 million placement. The issue price of A$0.36 per CDI is a 5.3% discount to the last closing price and a 3.6% discount to the five-day VWAP, while the 138.9 million new CDIs will increase the existing share count by approximately 14.9%.
The placement is not simply a corporate cash buffer. PLC plans to direct A$27 million, or 54% of the proceeds, towards SEZ precinct and port expansion work, tenant and strategic-partner engagement, a global expression of interest for industrial users, land subdivision and port design. A further A$10 million is earmarked for Central Cement Project early works and pre-FID costs, with A$10.8 million allocated to corporate costs, DFC transaction work and general working capital.
DFC term sheet adds a conditional financing pathway
Alongside the equity raising, PLC has signed a non-binding term sheet with the United States International Development Finance Corporation for a proposed US$15 million senior unsecured convertible note. The note would run for eight years and carry interest of 8% a year, payable in cash or capitalised at PLC’s election. DFC would be able to convert at A$0.42 per CDI, a 15% premium to the 20-day VWAP cited in the announcement, subject to a 29.99% ownership cap.
The proposed note would fund pre-development work across the lime, cement and international port projects, including environmental and social impact assessments, engineering and project preparation. It would also give DFC a right of first refusal over future financing for those facilities. That is a potentially important financing relationship, but it is not a commitment to provide the much larger project-level funding PLC may require: the company has described future debt requirements of up to US$400 million as indicative only.
Lime production and cement decision remain the near-term tests
PLC says construction of the Central Lime Project will continue, with first production still targeted for late Q1 to Q2 CY2027. The project recently moved into its equipment installation phase, after more than half of its major kiln and process plant materials had been delivered, according to the Central Lime equipment installation update. The new placement is intended to support the remaining construction effort while the company develops the broader precinct.
Central Cement is also being pushed towards a final investment decision targeted for the first quarter of calendar 2027, with pre-construction and early works scheduled to begin this quarter. PLC is simultaneously targeting a final investment decision for the expanded international nine-berth port in the same quarter, although capital cost estimates and the funding plan are still being finalised. First binding agreements with precinct tenants are targeted for the fourth quarter of 2026.
Definitive DFC documents remain the key financing hurdle
The DFC arrangement is still at the conditional stage. It requires due diligence, internal management and board approvals, ASX in-principle advice on the note terms, sufficient placement capacity, environmental and social requirements and definitive documentation. PLC has granted DFC 60 days of exclusivity to complete due diligence and negotiate those documents, while any future project financing would require separate approvals, project FIDs and financing agreements.
Bottom Line?
The placement gives PLC runway to reach its next project milestones, but the larger financing story depends on converting the DFC term sheet into binding documents and securing capital for the port and cement build-out.
Questions in the middle?
- Will PLC execute definitive documentation for the DFC note within the 60-day exclusivity period?
- Can Central Lime reach first production in the late Q1 to Q2 CY2027 target window?
- What final capital structure and funding package will support the cement and international port projects?