Carnegie puts CETO buoyant actuator offshore in Spain

Renewable Energy By Victor Sage 4 min read

Carnegie Clean Energy has placed its CETO Buoyant Actuator offshore at BiMEP in Spain, completing the first deployment stage of its ACHIEVE Programme. The short campaign is designed to prove the logistics and marine procedures needed before a planned grid-connected deployment in European spring 2027.

  • CETO Buoyant Actuator deployed and moored at BiMEP, Spain
  • Stage 1 validates port approvals, towing, assembly and offshore installation
  • Retrieval remains dependent on weather and vessel availability
  • Completion unlocks ACHIEVE Programme milestones and associated funding payments
  • Full grid-connected CETO deployment remains planned for European spring 2027

CETO Actuator Reaches BiMEP Offshore Berth

Carnegie Clean Energy Limited (ASX:CCE) has moved its CETO wave-energy technology from the quayside to open water, successfully deploying the Buoyant Actuator at the Biscay Marine Energy Platform in the Basque Country. The device was towed from the Port of Bilbao on Saturday and connected to a bespoke mooring and anchor system at Carnegie’s pre-permitted offshore berth.

“Carnegie’s CETO Buoyant Actuator has been deployed and is now offshore at the Biscay Marine Energy Platform (BiMEP) in the Basque Country, Spain.”Caption and image © Carnegie Clean Energy Limited. From “Successful Stage 1 Deployment”, 16 Nov 2026.

The milestone completes the first offshore deployment stage of the ACHIEVE Programme, following the fabrication of the CETO buoyant actuator. Carnegie had previously said the full system would target grid connection in European spring 2027, but the current campaign is deliberately narrower: the actuator will remain offshore only briefly before retrieval at the end of a suitable weather window.

Short Campaign Tests Marine Execution

Stage 1 is less a power-generation demonstration than an operational rehearsal. Carnegie used the campaign to test local port and maritime authorisations, supply-chain coordination, quayside assembly, heavy lifting, towing, vessel coordination, offshore mooring and installation procedures.

Image © Carnegie Clean Energy Limited. From “Successful Stage 1 Deployment”, 16 Nov 2026.

The three modular sections were transported from a local Basque fabricator to Bilbao, assembled at the port and lowered into the water by crane before being towed to BiMEP. The company said the work gave its team practical experience in managing offshore operations in the Basque Country and increased its certainty around the next deployment.

That distinction matters. The announcement does not report electricity generation, grid-connected operation, long-duration reliability or performance data from the CETO system. It describes a successful installation and logistics campaign, while the more demanding test of the integrated technology remains ahead.

Retrieval and Grid Connection Remain Ahead

Carnegie plans to retrieve the actuator and tow it back to port once weather conditions and vessel availability allow. Over the European winter, the unit will remain onshore while the power take-off modules undergo final testing with the electrical module, including simulated ocean-condition checks of mechanical, electrical, control and communications functions.

The company expects to deploy the fully integrated CETO system and connect it to the grid in European spring 2027. Completing Stage 1 also unlocks ACHIEVE Programme milestones and associated funding payments, although the announcement does not disclose the value or timing of those payments. The next meaningful evidence will therefore come from a safe retrieval, the onshore test results and whether the Stage 2 schedule holds.

Bottom Line?

Stage 1 removes a layer of deployment risk, but it does not yet prove grid-connected output or long-term CETO performance. Retrieval and the planned spring 2027 installation are the next hard tests.

Questions in the middle?

  • Can Carnegie complete retrieval within the available weather and vessel window?
  • What will the onshore PTO and electrical-module testing reveal before Stage 2?
  • When will the ACHIEVE milestone funding be recognised and in what amount?

Sources