PFI secures Stryker tenant for $25 million Harris Road redevelopment

Property for Industry has secured a 10-year Stryker lease for the first stage of its Harris Road redevelopment, with approximately $25 million of incremental investment planned. The industrial landlord will also pay a 2.40 cents per share first-quarter FY27 dividend as it reports progress on roughly half of upcoming lease expiries.

  • 2.40 cents per share first-quarter FY27 dividend
  • Record date of 23 November and payment on 2 December 2026
  • 10-year Stryker New Zealand lease at Harris Road
  • Approximately $25 million Stage 1 redevelopment investment
  • Target yield on cost of approximately 6.5%
An image related to Property for Industry Limited A photo of the logo for Property for Industry Add us as a preferred source on Google
Image © middle. Logo © respective owner.

Stryker lease anchors $25 million Harris Road redevelopment

Property for Industry Limited (NZX:PFI) has committed to the first stage of a roughly $25 million redevelopment at 92-98 Harris Road, East Tamaki, after securing a 10-year lease with Stryker New Zealand. Stage 1 is scheduled to begin in December 2026 and is expected to be completed in the third quarter of FY28.

PFI expects the project to deliver a yield on cost of approximately 6.5%, including land. The company said the redevelopment is expected to generate returns above its investment hurdle rates and described it as an attractive use of capital relative to alternatives, including an on-market share buy-back. The announcement does not specify the lease commencement date or provide the projected returns beyond that yield measure.

The deal gives PFI a committed occupier for the first stage, rather than leaving the redevelopment dependent on future leasing. Stryker New Zealand is described as part of a global medical technology business, but the filing does not disclose the rent, incentives or the precise scope of later redevelopment stages.

Half of FY27 expiries secured or under negotiation

PFI said around half of its FY27 lease expiries were either secured or in active negotiations as at 16 November. That progress matters for an industrial landlord because it reduces the amount of near-term rental income still exposed to vacancy or renegotiation, although the company has not disclosed the split between completed deals and negotiations.

At 670-680 Rosebank Road in Avondale, commercial terms have been agreed with a national occupier that also has an international presence. Documentation is well advanced for a long-term lease representing about 1.4% of contract rent, with commencement scheduled for April 2027.

PFI has also extended $2.4 million, or 2.0% of contract rent expiring in future years, by a weighted average of approximately 5.7 years. The package includes a further five-year renewal of EBOS' lease at 58 Richard Pearse Drive, Mangere, from October 2029, providing eight years of term certain over about 1.3% of contract rent.

Quarterly dividend set at 2.40 cents per share

The board has declared a first-quarter FY27 cash dividend of 2.40 cents per share, with 0.40 cents of imputation credits attached. Non-resident shareholders will receive a supplementary dividend of 0.18 cents per share. The record date is 23 November 2026 and payment is due on 2 December; the dividend reinvestment scheme will not operate for this distribution.

The payout continues the income focus highlighted in PFI's FY26 dividend increase, when the company reported a 10.5% rise in its full-year dividend. The more consequential question now shifts to execution: whether the Harris Road project can stay within its planned investment and timing parameters while the remaining FY27 expiries move from negotiation into signed leases.

Get NZX:PFI news the moment it breaks

Instant push notifications No waitlist Free
Download on the App Store iPhone & iPad
Get it on Google Play Android
Email alerts

Bottom Line?

PFI has paired a defined near-term dividend with a fully committed redevelopment, but the next test is delivery of the Harris Road project and conversion of lease negotiations into secured income.

Questions in the middle?

  • When will the Stryker lease commence, and what rent or incentives will it contribute to PFI's income profile?
  • Can Stage 1 Harris Road be completed by the third quarter of FY28 within the approximately $25 million investment envelope?
  • How much of the remaining FY27 expiry pool will be converted into signed leases rather than remaining in negotiation?