Strike moves South Erregulla toward first power and revenue

Energy By Maxwell Dee 3 min read

Strike Energy has scheduled grid energisation of its 85 MW South Erregulla Power Plant for 20 November, bringing the project to the threshold of revenue generation. AEMO testing will still stand between energisation and full commercial operations, but Strike says electricity revenue can begin during the six to eight-week certification process.

  • Grid energisation scheduled for 20 November 2026
  • AEMO hold-point testing expected to take six to eight weeks
  • Revenue generation can begin during testing as production ramps up
  • Contracted capacity revenue estimated at approximately $12 million in CY27, $31 million in CY28 and $39 million in CY29
  • Electricity sales provide additional upside, but the company’s CY29 scenario is illustrative rather than a forecast

South Erregulla reaches grid energisation stage

Strike Energy Limited (ASX:STX) is approaching the point at which its 85 MW South Erregulla Power Plant can start generating revenue, with grid energisation scheduled for 20 November in conjunction with Western Power. The milestone would move the project out of construction and into the final stages of commissioning.

The announcement advances the timetable previously flagged for the project. Strike’s November energisation target is now tied to a specific date, although energisation itself is not the same as full commercial operation.

AEMO testing creates a revenue ramp

Following energisation, the Australian Energy Market Operator is expected to begin hold-point testing immediately. Strike estimates that process will take six to eight weeks and says production can ramp up through the certification program, allowing revenue generation to start before the plant receives final approval for full commercial operations.

That distinction matters. Capacity Credit payments are due to begin only after AEMO testing concludes and an interim authority to generate is issued, while electricity sales may commence during the testing period at approved production levels. The timing and pace of that ramp remain subject to the testing process and operating approvals.

Capacity credits provide a contracted earnings base

Strike says South Erregulla has secured Capacity Credits for its full 85 MW output under Western Australia’s Reserve Capacity Mechanism. The credits are fixed on a rolling two-year lookahead basis, meaning the associated revenue is not dependent on dispatch volumes or wholesale electricity prices.

The company estimates contracted capacity revenue of approximately $12 million in Capacity Year 2027, pro rata on an assumed January 2027 commencement, rising to $31 million in CY28 and $39 million in CY29. Payments are expected weekly. Electricity sales would sit on top of that base, with Strike presenting an illustrative CY29 scenario of about $36 million in electricity sales alongside $39 million in capacity revenue. The company says that scenario assumes 10 hours of operation per day at an average electricity price of about $110 per megawatt-hour and is not a forecast.

Gas-to-power strategy approaches its first cash test

The plant is located beside Strike’s wholly owned South Erregulla gas field, and the company says direct wellhead gas is expected to support low operating costs and strong EBITDA margins. That configuration is central to Strike’s plan to convert its gas resources into downstream power infrastructure and recurring cash flow.

It also raises the importance of execution over the next several weeks. The immediate markers are whether energisation occurs as scheduled, how quickly AEMO testing permits production to ramp, and when the interim authority to generate is issued. Until those steps are completed, the projected revenue profile remains a forward-looking target rather than operating cash already in hand.

Bottom Line?

The key transition is now close: energisation may unlock early electricity sales, but the durability of Strike’s projected cash flow depends on AEMO certification and the speed of the production ramp.

Questions in the middle?

  • Will South Erregulla achieve the scheduled 20 November energisation without further commissioning delays?
  • How quickly will AEMO testing allow production to ramp toward the plant’s full 85 MW capacity?
  • When will the interim authority to generate be issued, allowing Capacity Credit payments to begin?