Strike moves South Erregulla toward first power and revenue

9:01am on Monday 16th of November, 2026 AEDT • Energy
Read Story

Strike moves South Erregulla toward first power and revenue

9:01am on Monday 16th of November, 2026 AEDT
Key Points
  • Grid energisation scheduled for 20 November 2026
  • AEMO hold-point testing expected to take six to eight weeks
  • Revenue generation can begin during testing as production ramps up
  • Contracted capacity revenue estimated at approximately $12 million in CY27, $31 million in CY28 and $39 million in CY29