Tungsten Mining’s Watershed project has emerged from its definitive feasibility study with a pre-tax NPV of A$1.57 billion and a June 2027 production target. The economics are compelling, but the company still needs about A$255 million, binding offtake and a final investment decision to turn the model into a mine.
- A$1.569 billion pre-tax NPV and 70% pre-tax IRR at a US$1,500/mtu tungsten price
- 36.6 million-tonne Probable Ore Reserve supporting 13.1 years of processing
- A$206.6 million in go-forward pre-production capital, excluding A$57.8 million already committed
- Approximately A$255 million of additional funding remains required
- First production targeted for June 2027, subject to funding and December 2026 FID
Watershed clears the feasibility hurdle
Tungsten Mining NL (ASX:TGN) has put a striking number on its Watershed project: A$1.569 billion of pre-tax NPV at an 8% discount rate, with a 70% pre-tax IRR and payback 18 months after first revenue. The Far North Queensland project’s base case assumes a life-of-mine average tungsten APT price of US$1,500 per mtu, well below the US$2,675/mtu spot price cited in the study.
On the company’s illustrative spot case, the pre-tax NPV rises to A$4.121 billion and the payback period falls to eight months. That is useful as a measure of price exposure, but it is not the underwriting case. The DFS also reports a post-tax NPV of A$1.105 billion and a post-tax IRR of 57%.
A long-life mine with a low stated cost base
Watershed’s Probable Ore Reserve stands at 36.6 million tonnes grading 0.124% WO₃, containing 45.5 kilotonnes of tungsten trioxide. The study schedules 31,279 tonnes of recovered WO₃ over a 13.1-year processing life, with steady-state production averaging about 2,719 tonnes a year between 2029 and 2037.
The operation is designed around a conventional open pit feeding a 3.5 million-tonne-per-year plant. X-ray transmission sorting, dense media separation, spirals and downstream beneficiation are intended to produce a concentrate grading more than 50% WO₃. The DFS puts life-of-mine C1 cash costs at US$440 per mtu and all-in sustaining costs at US$538 per mtu, with a 62% pre-tax operating margin in the base case.
Approvals and early works have moved the project beyond paper
The project has secured its principal approvals, while early works, civil activity, accommodation establishment and procurement of long-lead process equipment are under way. That progress builds on the Watershed early construction reported in October, when the company said early construction had begun and financing proposals could support roughly 70% gearing.
Tungsten Mining says A$57.8 million has been committed to site establishment, civil works, accommodation and long-lead items. The remaining go-forward pre-production capital is estimated at A$206.6 million, while the project’s peak funding requirement is approximately A$277 million, leaving about A$255 million still to be funded after expenditure to date.
Funding and offtake remain the decisive gates
Non-binding debt term sheets support up to 70% project gearing, and the company is considering senior debt, new equity, strategic investment, offtake-linked funding, government support and equipment finance. That is a broader financing menu than a simple equity raise, but none of the debt proposals is binding and the announcement warns that funding may be available only on terms that dilute existing shareholders or otherwise affect their value. The company has previously outlined its Watershed debt pathway, with proposals potentially covering up to 70% of pre-production capital.
Offtake discussions are also advancing, with concentrate samples sent to counterparties in Europe, South-East Asia, the United States and Japan. Tungsten Mining says initial refiner feedback has been positive, but no binding offtake agreement has been signed. Final product specifications, payability and contract volumes therefore remain open commercial variables rather than settled project inputs.
The headline economics carry two important qualifications
About 10% of the mill feed underpinning the base-case production target is classified as Inferred Mineral Resources. The company says it has reasonable grounds for including that material, but also acknowledges the low geological confidence and the possibility that the production target will not be realised. An Ore Reserve-only case, excluding the Inferred component, produces a pre-tax NPV of A$1.4 billion, compared with A$1.569 billion for the base case.
The next test is therefore less about whether Watershed can produce a large spreadsheet return and more about whether the financing, offtake and construction sequence can be locked together. Tungsten Mining is targeting FID in December 2026 and first production in June 2027, leaving a compressed path from non-binding proposals to funded construction and commissioning.
Bottom Line?
The DFS materially strengthens Watershed’s development case, but December’s FID target now depends on converting indicative debt and offtake discussions into binding commitments without excessive dilution.
Questions in the middle?
- Can Tungsten Mining secure the approximately A$255 million still required on terms that preserve shareholder value?
- Will binding offtake agreements support project finance and confirm acceptable payability and product specifications?
- Can the company deliver June 2027 first production while completing construction, commissioning and resource-definition work on schedule?