Home › Mining › Black Rock Mining (ASX:BKT)

Black Rock finds runway to advance Mahenge earthworks

Mining By Maxwell Dee 3 min read

Black Rock Mining has secured a three-month US$5 million drawdown from Tanzanian lender CRDB to fund early works at its Mahenge graphite project. The cash advances earthworks before the wet season, but full project funding and a Final Investment Decision remain outstanding.

  • US$5m CRDB bridge drawdown for Mahenge early works
  • Three-month facility priced at six-month SOFR plus 8%
  • Bulk earthworks mobilisation planned before Tanzania’s wet season
  • Power line corridor survey and profiling completed
  • Final project funding and FID remain unresolved

CRDB funding unlocks immediate Mahenge work

Black Rock Mining Limited (ASX:BKT) has bought itself a short window to keep Mahenge moving, securing a US$5 million early drawdown from Tanzanian commercial bank CRDB. The bridge funding is earmarked for immediate project requirements, including site preparation and the early works program at the company’s graphite project.

The facility runs for three months from first drawdown and carries interest at the six-month Secured Overnight Financing Rate plus 8% a year. It is repayable by the end of that period, or earlier if CRDB demands repayment following an event of default. The loan is secured by first-ranking debentures over the borrower’s assets, mining licences and motor vehicles, with security registered for US$6.25 million plus interest, costs and other charges.

Short-dated cash meets a wet-season deadline

The immediate purpose is practical rather than transformational: mobilise bulk earthworks contractor Taifa Mining and Civils before the coming wet season disrupts access and construction activity. Black Rock said early works are already underway and are intended to support a faster transition into the main construction program once funding is complete and FID is reached.

The drawdown follows the company’s revised Mahenge funding plan, which included a revised US$40 million binding POSCO subscription and a non-binding US$70 million term sheet with African Critical Minerals. Those arrangements improve the funding picture, but the CRDB facility itself is a bridge, not evidence that the full project financing package has closed.

Power and procurement work moves closer to construction

Black Rock said the early works push is accompanied by progress on project readiness. The Tanzanian Mining Commission has approved the award of all 11 long-lead original equipment manufacturer packages, which the company says are ready for award once FID is reached. The power line early works phase, including corridor surveying, tower spotting and line profiles, has also been completed for the planned Ifakara-to-Mahenge 220kV transmission connection.

The next pre-FID step for that connection is to complete front-end engineering design and tender the substation and transmission-line engineering, procurement and construction contracts. The company has also continued community engagement around the site, according to the announcement.

Repayment pressure remains the immediate test

Once the bridge loan is repaid, Black Rock said its broader banking-syndicate facility involving CRDB, the Development Bank of Southern Africa and the Industrial Development Corporation will take effect. That makes the three-month repayment point important: the company must either complete the next stage of funding, refinance or secure an extension while still progressing toward FID.

Black Rock Managing Director John de Vries said the drawdown provided “financial runway and operational flexibility” while funding discussions continued. The filing does not set out a completed timetable for the remaining financing, so the next hard evidence will be the Mining Commission acknowledgement, earthworks mobilisation and binding commitments for the balance of Mahenge’s capital needs.

Bottom Line?

The US$5m drawdown keeps Mahenge’s early works alive, but its short maturity leaves funding close and FID as the decisive next milestones.

Questions in the middle?

  • Will the Mining Commission formally acknowledge the bridge security and when will the first drawdown occur?
  • Can Black Rock convert the remaining funding discussions into binding commitments before the three-month repayment date?
  • Will bulk earthworks mobilisation proceed on schedule before the wet season despite the unresolved full project funding package?