PDI Gold clears Guinea permit hurdle as Bankan moves toward construction

Mining By Maxwell Dee 4 min read

PDI Gold has received Guinea’s final key exploitation permits for its Bankan development and Mansounia deposit, clearing the stated regulatory path to construction and mining. Bankan’s first gold remains targeted for mid-2028, while the company plans to release an updated schedule and capital estimate in early 2027.

  • Guinea grants 15-year exploitation permits for Bankan and Mansounia
  • Bankan construction and Mansounia mining preparations to accelerate
  • Bankan targets approximately 250,000oz of annual production
  • First Bankan gold targeted for mid-2028
  • US$463 million DFS capital estimate not currently expected to increase

Guinea grants permits for two PDI Gold projects

PDI Gold Limited (ASX:PDI; TSX:PDI) has cleared the regulatory hurdle that had stood between its flagship Bankan project and construction, with Guinea granting exploitation permits for Bankan and the Mansounia deposit at the operating Kiniéro mine.

“Bankan, Mansounia and existing Kiniéro Exploitation Permits.”Caption and image © Pdi Gold Limited. From “Bankan and Mansounia Exploitation Permits Granted”, 17 Nov 2026.

The permits are described by PDI Gold as the final key approvals required to commence Bankan construction and Mansounia mining. The Bankan permit covers 98.6 square kilometres and runs for an initial 15 years, while the two Mansounia permits cover 44.7 square kilometres and 26.5 square kilometres, also with initial 15-year terms. Guinea is entitled to a 15% interest in the exploitation permits under the country’s Mining Code.

Bankan moves from readiness into execution

The announcement shifts Bankan from a permit-dependent development story into an execution program. The board has endorsed an acceleration of procurement, detailed engineering and compensation activities, with the aim of starting full construction as soon as practicable.

That work was already under way before the permits were granted. PDI Gold said detailed engineering was advancing across the process plant, power station and tailings storage facility, while US$18 million in down payments had been made for the semi-autogenous grinding and ball mills and a 40MW power station. The company had also continued environmental and social workstreams.

The permit decision resolves the issue highlighted in the company’s earlier Bankan permit hurdle coverage, which described the project as advanced but still dependent on Guinea’s approval. PDI Gold also previously reported that Bankan’s front-end engineering and design work had been completed and key contracts awarded.

Updated Bankan economics due in early 2027

Bankan’s existing definitive feasibility study points to production of about 250,000 ounces of gold a year over a 12-year mine life, based on upfront capital of US$463 million and all-in sustaining costs of US$1,111 an ounce at a gold price of US$3,300 an ounce. PDI Gold said it does not currently anticipate an increase to that capital estimate and is pursuing initiatives to reduce it.

Those figures are not yet the final execution case. An optimised implementation schedule, capital cost estimate and mining and production profile are being prepared for release in early 2027. PDI Gold currently expects first gold in mid-2028, but that timing and the capital benchmark remain forward-looking and subject to the updated work.

Mansounia adds near-term production flexibility

At Kiniéro, preparation to begin mining Mansounia will start immediately. The deposit is described as near-surface and low strip-ratio, with grade-control drilling completed during construction and initial pit designs already in place.

Mansounia carries a Probable Ore Reserve of 0.48 million ounces within an Indicated Mineral Resource of 0.68 million ounces and an Inferred Mineral Resource of 1.00 million ounces. PDI Gold said bringing it into the mine plan presents an opportunity to optimise Kiniéro’s near-term production and cost profile, rather than waiting for the much larger Bankan project to reach production.

Kiniéro provides the operating test

PDI Gold is relying on Kiniéro’s recent ramp-up as evidence of its execution platform in Guinea. The mine achieved first gold in December 2025, reached commercial production in February 2026 and has continued to exceed its 6 million tonnes per annum nameplate processing capacity. The company remains on track for 2026 guidance of 157,000 to 174,000 ounces poured at an all-in sustaining cost of US$1,100 to US$1,300 an ounce.

Once Bankan is fully operating, PDI Gold is targeting more than 400,000 ounces of annual production from its Guinea hub. The next meaningful test is no longer whether the permits will arrive, but whether procurement, compensation, construction funding and site execution can convert regulatory clearance into the mid-2028 pour without eroding the feasibility study’s capital assumptions.

Bottom Line?

The permit risk has receded, but the early 2027 Bankan update will determine whether the project’s promised scale still fits its US$463 million capital frame and mid-2028 schedule.

Questions in the middle?

  • Will the optimised Bankan schedule preserve the mid-2028 first-gold target?
  • Does the updated capital estimate confirm or change the US$463 million DFS benchmark?
  • How quickly can Mansounia contribute to Kiniéro’s production and cost profile?