Corazon opens a modular path to process Chalice gold on site

Mining By Maxwell Dee 5 min read

Corazon Mining is evaluating a build-own-operate carbon-in-leach plant at its Chalice Gold Project, with an initial 600,000-tonne annual capacity and expansion potential to 1.8 million tonnes. The proposal could reduce upfront processing capital, but remains non-binding and depends on metallurgy, approvals, funding and a definitive contract.

  • 600,000tpa modular CIL plant proposed at Chalice
  • Expansion potential to 1.8Mtpa in 600,000tpa modules
  • BOO proposal targeted for April 2027
  • Potential processing commencement targeted for Q1 2028
  • Interim toll treatment option retained, but not guaranteed

600ktpa Plant Would Give Chalice a Dedicated Processing Option

Corazon Mining Limited (ASX:CZN) is weighing a dedicated processing route for its Chalice Gold Project, signing a non-binding memorandum of understanding with Modular Gold Solutions to assess a 600,000-tonne-per-year modular carbon-in-leach plant. The proposed facility could be expanded in 600,000tpa increments to 1.8 million tonnes per year, although those figures describe plant design capacity rather than a production target or forecast.

Image © Macro Metals Limited. From “CZN: Chalice Modular Plant MOU”, 17 Nov 2026.

The proposed build-own-operate structure would see MGS fund, build and operate the plant, while Corazon would pay a mobilisation fee and throughput-based processing charges under a proposed minimum 24-month term. That structure has the potential to reduce Corazon’s upfront processing capital compared with owning a conventional plant, but the announcement does not yet provide the fees, processing rates or capital and operating cost estimates that would determine whether the model is economically attractive.

Chalice Resource and Metallurgy Remain the Key Tests

Chalice has a JORC 2012 Mineral Resource of 191,000 ounces at 2.74 grams per tonne of gold on a granted mining lease, alongside a historical production record of about 645,000 ounces at an average grade of approximately 5.4g/t. Corazon acquired the project from Westgold Resources in July 2026 and is running resource-growth drilling and pre-production studies in parallel with the processing evaluation.

“Corazon Mining's Western Australian Gold Project locations.”Caption and image © Macro Metals Limited. From “CZN: Chalice Modular Plant MOU”, 17 Nov 2026.
“Indicative modular plant layout and expansion configuration (image indicative only).”Caption and image © Macro Metals Limited. From “CZN: Chalice Modular Plant MOU”, 17 Nov 2026.

The proposed flowsheet would include crushing, screening, milling, gravity recovery, carbon-in-leach, thickening, tailings pumping and an on-site gold room. Historical processing achieved recoveries in the mid-90% range, but Corazon says new metallurgical test work is required to confirm recovery, throughput and reagent consumption for the proposed plant. Until that work is complete, the historical recovery data offers useful evidence rather than a confirmed operating assumption.

April 2027 BOO Proposal Sets the Next Decision Point

The parties intend to spend the coming months assessing the mine plan, ore schedule, metallurgical data, plant design, approvals, tailings requirements and commercial responsibilities. Preliminary capital and operating cost estimates are targeted for March 2027, followed by a BOO proposal in April. The MoU itself runs for 12 months, while either party can terminate on 10 business days’ notice after the first three months in specified circumstances.

Any plant deployment would still require satisfactory technical and commercial outcomes, agreed funding and responsibilities, board approvals, regulatory approvals and a binding BOO contract. Corazon is targeting processing commencement in the first quarter of 2028, but that timing is expressly indicative. The proposed plant would also require approvals under Western Australian mining and environmental legislation, including works approval and licensing.

Toll Treatment Keeps an Alternative Route Open

Corazon has preserved the right to pursue interim toll treatment at third-party facilities while the MGS evaluation proceeds. Chalice is located within about 130 kilometres of seven operating processing facilities, including Westgold’s Higginsville CIL facility roughly 22 kilometres away, but Corazon does not currently have a right to use any of them and gives no assurance that capacity will be available on acceptable terms.

That optionality matters because the BOO proposal is not yet a commitment to build a plant, while toll treatment could provide a separate route if available. The commercial comparison will ultimately turn on processing rates, mobilisation and demobilisation costs, transport, availability, tailings obligations and the scale of Chalice’s mine plan. The next meaningful evidence will be the metallurgical results, cost estimates and April proposal rather than the MoU alone.

Bottom Line?

The MoU offers Corazon a potentially lower-capital processing pathway, but April 2027 costings and metallurgy will determine whether the concept can move beyond an attractive design proposition.

Questions in the middle?

  • Will Chalice’s updated metallurgy support the proposed CIL flowsheet and its planned throughput?
  • Will the BOO model prove cheaper and more reliable than available toll-treatment alternatives?
  • Can Corazon secure funding, approvals and a binding contract in time to support the Q1 2028 target?