Larvotto wins US$30m backing as Hillgrove moves towards gold doré

Larvotto Resources has received US$30 million from Glencore and Wogen Resources against future gold and antimony concentrate deliveries, strengthening liquidity during Hillgrove’s commissioning phase. Gold concentrate shipments have begun, while first gold doré remains targeted for late November.

  • US$15 million received from each offtake partner
  • Prepayments to be settled through future concentrate deliveries
  • Gold deliveries to Glencore and antimony shipments to Wogen have commenced
  • Full production remains targeted by the end of December 2026
  • Tungsten testwork is set to begin in Canada
An image related to Larvotto Resources Limited A photo of the logo for Larvotto Resources Add us as a preferred source on Google
Image © middle. Logo © respective owner.

US$30m Arrives During Hillgrove Commissioning

Larvotto Resources Limited (ASX:LRV) has secured US$30 million in prepayments from its two Hillgrove offtake partners, giving the New South Wales operation more working-capital flexibility as it moves through a four-month commissioning phase. Glencore and Wogen Resources each provided US$15 million, with all funds now received.

The arrangement is not described as a conventional equity raising. Instead, the prepayments are to be settled through future deliveries of gold and antimony concentrates to the respective partners, and remain available for 12 months. The announcement does not disclose the pricing mechanics, security arrangements or any repayment adjustments, saying only that the facilities were provided on usual commercial terms.

Gold and Antimony Sales Have Started

Hillgrove has already moved beyond an entirely pre-revenue commissioning story. Antimony concentrate shipments to Wogen began in October, while Larvotto has now commenced gold concentrate deliveries to Glencore. The gold shipment follows the project’s first gold concentrate delivery, which added a second saleable product as the processing plant ramped up.

Larvotto says the process plant is performing to plan, with tonnes and grades steadily improving. Antimony was commissioned first and is described as being close to forecast production levels, with tonnes and grade near optimal. The company is now concentrating on improving gold concentrate volumes and grades.

Gold Doré and Tungsten Are the Next Tests

The next near-term milestone is first gold doré production, which Larvotto expects in late November. Full production remains targeted for the end of December 2026, after an earlier commissioning delay caused by difficulties transporting critical equipment, including dry tailings filter presses. The company attributed that disruption to global shipping problems linked to the war in the Strait of Hormuz.

The new funding will also support tungsten metallurgical testwork and process-flow-sheet optimisation. About two tonnes of sample is expected to arrive by boat in Canada, where the work will begin. That programme is intended to advance Hillgrove towards tungsten production, but the announcement provides no production date or operating forecast for the potential fourth revenue stream.

The financing improves Larvotto’s immediate liquidity while the plant is still being commissioned, but it also ties the prepayments to future concentrate deliveries. The key evidence now will be operational: whether gold doré arrives on schedule, whether concentrate tonnes and grades continue to improve, and whether the December full-production target survives the final stretch of commissioning.

Get ASX:LRV news the moment it breaks

Instant push notifications No waitlist Free
Download on the App Store iPhone & iPad
Get it on Google Play Android
Email alerts

Bottom Line?

The US$30m provides useful runway, but Hillgrove must now convert commissioning progress into consistent deliveries and gold doré production before the prepayment commitment becomes the next test.

Questions in the middle?

  • Can Hillgrove produce first gold doré in late November after the earlier equipment-related delay?
  • Will gold concentrate tonnes and grades reach the company’s scheduled forecasts during the remaining commissioning period?
  • How quickly can tungsten testwork translate into a defined production pathway and an additional revenue stream?

Sources