Medallion Metals has begun a 9,000-metre drilling campaign at Kundip, including two deep holes testing whether known gold-copper deposits sit above a larger system. The company is also moving towards first gold from third-party ore at Cosmic Boy in early December, while underground development advances at Kundip.

  • 9,000m Kundip drilling program begins, including two EIS-supported deep diamond holes
  • Lounge Lizard drilling accelerates ahead of a maiden resource estimate due in December
  • Kundip civil works are 90% complete, with the first portal cut scheduled for early December
  • First gold from third-party material at Cosmic Boy is expected in early December
  • Ravensthorpe and Forrestania development is approximately 40% complete and remains on schedule and budget

Kundip drilling targets deeper gold-copper system

Medallion Metals Limited (ASX:MM8) has started a 9,000-metre drilling program at the Kundip Mining Centre, putting the focus back on the resource upside beneath the deposits that underpin its planned underground operation. The campaign will test extensions to known high-grade gold-copper mineralisation and deeper targets identified through structural interpretation and electromagnetic surveys.

“Hillsborough Deeps/Harbour View cross section showing reported drilling results and mineralised trends.1.”Caption and image © Medallion Metals Limited. From “Kundip Drilling Commences as EPS Nears First Gold”, 18 Nov 2026.

The most consequential holes are two deep diamond holes supported by $180,000 in co-funding from the Western Australian Government’s Exploration Incentive Scheme. One, targeting Hillsborough Deeps and Harbour View, is planned to reach about 800 metres and test a modelled EM conductor. The second, at Gem Restored, is planned to reach about 600 metres and investigate a 350-metre down-plunge extension below known high-grade mineralisation.

The geological case is prospective but unproven. Fewer than 4% of historical drill holes at Kundip extend below 250 metres, while an earlier Hillsborough Deeps intersection returned 11.7 metres at 3.5 grams per tonne gold and 2.2% copper from 440 metres. Medallion points to porphyry intrusions, high-temperature mineral assemblages and massive sulphide breccias as evidence that the existing deposits could represent the upper part of a larger system. The new drilling will determine whether that interpretation survives contact with the rock.

Lounge Lizard drilling moves towards December resource

At Lounge Lizard, a 3,000-metre diamond program is already 1,500 metres complete, and a second rig is being mobilised. The work is designed to test extensions to high-grade gold mineralisation, confirm historical results and provide data for a maiden Mineral Resource Estimate expected in December. This follows the earlier Kundip drilling plan, which had identified a 9,000-metre resource-extension campaign as an imminent catalyst.

Medallion says civil works are progressing to allow drilling from the existing pit floor and to provide a platform for potential underground access. The intended prize is not merely a larger exploration inventory: the company says the resource estimate will help assess whether Lounge Lizard could support a future mining operation supplying the Cosmic Boy concentrator and contribute to longer-term production and mine-life extensions.

Portal cut and first Cosmic Boy gold approach

“Kundip box-cut showing jumbo ground support drilling and completed excavation and shotcreting.”Caption and image © Medallion Metals Limited. From “Kundip Drilling Commences as EPS Nears First Gold”, 18 Nov 2026.

Development is approximately 40% complete across the Ravensthorpe Gold Project and Forrestania Gold Project, with the company reporting progress on schedule and budget. Kundip civil works are about 90% complete, Macmahon has mobilised and ground support work is under way in the box-cut ahead of the first portal cut, scheduled for the first week of December. About five months of decline development is then expected to reach the orebody, keeping first underground ore targeted for the second quarter of calendar 2027.

Cosmic Boy is approaching an earlier operational test. The initial third-party ore campaign is progressing through leaching under the Early Processing Strategy, with first gold expected in early December. About 55,000 tonnes of material is stockpiled on the ROM pad, including 50,000 tonnes of third-party material and 5,000 tonnes from Medallion’s Teddy Bear stockpiles. Expansion and modification work by GR Engineering Services is approximately 35% complete, with the plant transition to full production still planned for mid-2027. The near-term question is whether commissioning can establish reliable operating performance before Kundip ore arrives.

Bottom Line?

December brings several tests at once: first third-party gold, the Kundip portal cut and the Lounge Lizard resource estimate. None yet guarantees a larger mine, but together they should begin separating exploration potential from executable production capacity.

Questions in the middle?

  • Will the deep Kundip holes confirm a larger mineralised system, or mainly extend known deposits?
  • What scale and grade will the Lounge Lizard maiden resource estimate establish in December?
  • Can Cosmic Boy process third-party material consistently before Kundip ore is delivered in 2027?

Sources