Meeka’s Murchison sorter turns low-grade ore into a richer mill feed
Meeka Metals has produced a 4.39 g/t gold product from 0.86 g/t feed during early commissioning of its Murchison ore sorter. The system captured 80% to 90% of contained gold in just 16% of the feed mass, although operating hours and optimisation remain unfinished.
- 4.39 g/t gold product from 0.86 g/t feed
- 80% to 90% of gold recovered into 16% of feed mass
- 5,412 tonnes treated since first production on 26 October
- Throughput averaged 60 tonnes per hour
- Commissioning focus shifts to operating hours and settings optimisation
Add us as a preferred source on Google
Ore Sorter Concentrates Gold Into 16% of Feed
Meeka Metals Limited (ASX:MEK) has reported an early commissioning result that gives its Murchison processing upgrade a sharper edge: low-grade development ore averaging 0.86 g/t gold was converted into a product averaging 4.39 g/t. The sorter recovered 80% to 90% of the gold in the feed into 16% of the mass, while the reject stream averaged 0.18 g/t gold.

Between first production on 26 October and 15 November, the Steinert multi-sensor sorter treated 5,412 tonnes and produced 882 tonnes of product. Throughput averaged 60 tonnes per hour, with 3,976 tonnes processed in the week to 15 November after two-shift operations began on 10 November.
Commissioning Results Still Depend on Operating Hours
The result is encouraging, but it is not yet a steady-state production outcome. Meeka is drawing commissioning feed from an approximately 50,000-tonne low-grade stockpile built from underground development ore, and says the main opportunity now is to keep the sorter operating for more hours each day.
The company tested two settings. The High Grade setting produced a 4.31 g/t product from 0.97 g/t feed, while the Balanced setting delivered 4.42 g/t from 0.83 g/t feed. Those settings were run on different material, so Meeka says the difference in gold recovery still needs to be confirmed through further trials. Product and reject streams are sampled each shift and assayed at the company’s site laboratory.
Processing Upgrade Joins Underground Growth Plan
The sorter sits ahead of the mill in an expanded circuit that also includes additional crushing and a wash plant. Its role is to send the higher-grade product to the mill while stockpiling reject material for later processing, potentially allowing available mill capacity to be directed towards a smaller, richer stream. The filing reports the commissioning figures but does not quantify any resulting change in gold production, costs or cash flow.
The timing matters as Meeka shifts Murchison towards underground production. The company’s September-quarter update reported rising Andy Well underground output, while its Fairway decline development had first ore targeted for January 2027. Chief executive Tim Davidson said higher-grade sorter feed, growing Andy Well production and first Fairway ore are intended to support higher gold production at Murchison, although the latter timetable remains forward-looking.
Next Test Is Sustained Sorter Performance
For shareholders, the next useful data points are less dramatic than the initial five-fold grade increase but more important for assessing the upgrade: operating hours, tonnes processed, product grade, recovery and the effect on mill feed once commissioning is complete. The current figures come from initial production and assayed shifts, not a completed operating performance study.
Bottom Line?
The sorter has demonstrated strong early concentration, but its investment case now turns on whether Meeka can sustain the grade and recovery while materially increasing operating hours.
Questions in the middle?
- Can Meeka maintain 80% to 90% gold recovery as feed types and sorter settings change?
- How quickly can operating hours lift throughput beyond the commissioning average of 60 tonnes per hour?
- What effect will the higher-grade product have on mill performance, gold production and unit costs once commissioning is complete?