WA1 Resources’ pre-feasibility study has put a A$2.5 billion pre-tax NPV on its Luni niobium project, supported by a 20.3 million-tonne Probable Ore Reserve and a proposed 17-year mine life. The numbers are substantial, but construction funding, approvals, offtake and a final investment decision remain ahead.
- A$2.5 billion base-case pre-tax NPV and 29% IRR
- 20.3Mt Probable Ore Reserve grading 2.75% Nb₂O₅
- 20,000tpa ferroniobium production over 17.3 years
- A$1.069 billion pre-production capital estimate
- Funding, approvals and offtake remain unsecured
Luni clears the first major economic hurdle
WA1 Resources Ltd (ASX:WA1) has attached a sizeable price tag to its Luni niobium project, with a pre-feasibility study estimating a base-case pre-tax NPV8 of A$2.5 billion and a pre-tax IRR of 29%. At October 2026 spot pricing, the figures rise to A$3.0 billion and 32.7% respectively, although the company has not made a final investment decision and the study remains a PFS-level assessment.
The proposed operation would produce approximately 20,000 tonnes a year of ferroniobium for an initial 17.3-year mine life. The production target is supported entirely by a 20.3 million-tonne Probable Ore Reserve grading 2.75% Nb₂O₅, containing 558,000 tonnes of contained niobium pentoxide. That reserve is only a portion of Luni’s broader resource base, following the 220Mt Luni resource update, which reported 93Mt in the Indicated category.
A mine to ferroniobium supply chain
WA1’s base case is more ambitious than a concentrate-only mine. Ore would be extracted by conventional open-pit methods in Western Australia, processed into niobium concentrate at Luni, then moved by road and rail via Alice Springs and Adelaide to a proposed refining and conversion plant at Whyalla in South Australia.
The integrated route carries an estimated A$1.069 billion of pre-production capital, including A$770 million at Luni and A$299 million for the Whyalla facility. The remote mine would require a new approximately 110-kilometre access road, a 480-room village, upgraded aviation infrastructure and stand-alone power generation. Whyalla offers industrial infrastructure and transport links, but its final site, land arrangements, utilities and approvals are not yet secured.
The study assumes average EBITDA of A$479 million a year at a 55% margin and an average all-in sustaining cost of A$22,302 per tonne of ferroniobium, against a base-case price of US$30,225 per tonne. The capital estimate is an AACE Class 4 estimate with an indicative accuracy range of negative 20% to positive 30%, an important qualification when the headline NPV is more precise than the underlying engineering.
Price strength helps, but market entry is still unproven
WA1 has deliberately based the model on a long-term ferroniobium price below October spot levels and argues that Luni does not require a near-term supply deficit to enter the market. Its case rests on growth in steel demand, higher niobium intensity in high-strength steels and the appeal of supply diversification beyond Brazil and Canada.
That strategy still needs commercial validation. No binding offtake agreements have been signed, while the company’s own study identifies the market as highly concentrated and notes that incumbent producers retain spare capacity. The price sensitivity is material: a 30% reduction in the base-case niobium price cuts the modelled pre-tax IRR to 13.1% and NPV8 to approximately A$0.5 billion, assuming other inputs remain unchanged.
Approvals and financing now become the central test
WA1 enters the next phase with approximately A$113 million in cash, no debt and full ownership of Luni. It plans to advance detailed feasibility work alongside discussions covering commercial debt, export credit, government-backed funding, strategic investment and offtake-linked finance. No funding pathway has been selected, and the company has warned there is no guarantee that the required capital will be secured.
The regulatory work is equally unfinished. The next significant approvals step is referral to Western Australia’s Environmental Protection Authority, alongside the Mining Lease application, water and other statutory approvals. Negotiations with the Ngururrpa and Kiwirrkurra People are continuing under formal protocols, but the project agreements, access arrangements and benefit-sharing terms required for construction and operations remain subject to further negotiation and authorisation.
WA1’s next milestones are therefore less about finding another impressive number and more about converting this one into a financeable, permitted and commercially contracted project. A resource and Ore Reserve update is planned as drilling advances, while metallurgical scale-up, Whyalla site selection, product qualification and the detailed Feasibility Study will determine how much of the PFS value survives contact with execution.
Bottom Line?
The PFS gives WA1 a powerful economic platform, but the investment case now shifts from discovery and modelling to funding, approvals, customer qualification and construction risk.
Questions in the middle?
- Can WA1 secure binding offtake or strategic partnerships for a project whose planned output is large relative to forecast market growth?
- How will the AACE Class 4 capital estimate change as the remote mine, logistics corridor and Whyalla facility move into detailed engineering?
- Will resource upgrades and metallurgical work extend mine life or improve recovery without adding comparable capital and operating complexity?