Brookside Suttles wells clear 1,500 BOEPD milestone with costs below budget

Brookside Energy’s two Suttles Pad wells have lifted combined gross production beyond 1,500 BOEPD, while development costs remain about 15% below budget. The result is encouraging, but both wells are still cleaning up and their representative production rates have yet to be established.

  • Combined gross production exceeds 1,500 BOEPD
  • Production rises from the previous 1,200 BOEPD milestone
  • Suttles development costs track approximately 15% below budget
  • Sabres uses gas lift while Whalers continues to flow naturally
  • Representative initial production rates remain pending
An image related to Brookside Energy Limited A photo of the logo for Brookside Energy Add us as a preferred source on Google
Image © middle. Logo © respective owner.

Suttles wells pass 1,500 BOEPD

Brookside Energy Limited (ASX:BRK) has pushed combined gross production from its Sabres and Whalers wells at the Suttles Pad beyond 1,500 barrels of oil equivalent per day, up from the previously reported 1,200 BOEPD milestone. The company said the latest figure was recorded over a 24-hour period, with the liquids contribution remaining within its forecast range.

The increase marks the next step in a rapid early production ramp-up at the southern Oklahoma development. The wells had only recently reached the earlier 1,200 BOEPD milestone, although the current rate remains a combined gross figure rather than Brookside’s net production.

Flowback still clouds production profiles

Both wells remain in cleanup, with substantial completion water still being recovered. Sabres, targeting the Sycamore formation, is producing through conventional gas lift, while Whalers, targeting the Woodford, continues to flow naturally. Those differing arrangements, along with ongoing fluid recovery, mean the early production profiles are still developing.

Brookside therefore has not yet declared representative initial production rates. The company expects to provide those figures once flowback has progressed far enough to offer a more meaningful measure of well performance. That distinction matters: the current milestone is a useful operating datapoint, but it is not presented as a settled IP rate or a long-term production forecast.

Development costs remain 15% below budget

The other favourable metric is cost. Suttles development spending is tracking approximately 15% below budget, giving Brookside two positive variables at once: higher reported output and lower-than-planned development costs.

Managing Director and CEO David Prentice said, “Production continues to build, and with development costs tracking below budget, we're well positioned to deliver strong returns from Suttles.” He added that the key test would be how quickly the company recovers its investment and the cash the wells generate over their producing lives. Brookside said current production trends and economic assumptions put Suttles on track to deliver returns competitive with leading Anadarko Basin developments, but that assessment remains forward-looking.

Next test is stable output and cash generation

The coming months should clarify whether the production milestone survives the transition from cleanup to more representative operations. The company’s next updates will need to show how flowback progresses, how the liquids mix settles, and whether the below-budget development performance is maintained as the wells move into normal production.

Get ASX:BRK news the moment it breaks

Instant push notifications No waitlist Free
Download on the App Store iPhone & iPad
Get it on Google Play Android
Email alerts

Bottom Line?

The 1,500 BOEPD milestone and lower costs improve the early Suttles picture, but stable production rates and actual cash generation remain the decisive tests.

Questions in the middle?

  • How will Sabres and Whalers perform once completion-water recovery subsides?
  • When will Brookside report representative initial production rates for each well?
  • Can the 15% development-cost saving be sustained through the remaining ramp-up and operating phase?

Sources

1